These are the activities on the critical path:

Suggested Answer: C
Get Premium AACE-PSP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Critical Path Identification:
The critical path is the longest sequence of activities that determines the project's minimum duration.
Path: A B G H.
Exclusion of Other Options:
Paths involving F, J, or non-critical activities do not align with the longest duration.
Verification with PSP Guidelines: The PSP Study Guide emphasizes identifying the critical path for schedule optimization (Ref: PSP Study Guide, Chapter 2A: Critical Path Analysis)
12 comments · newest first
JE
Jesusa
3 months ago
I'm leaning towards C. A, B, G, & H make sense for the timeline.
EL
Elouise
3 months ago
I feel A is right. A, D, & I are key activities.
TR
Truman
3 months ago
I think it's B. A, C, E, & H seem crucial.
PH
Phillip
4 months ago
Not convinced about D being critical.
DE
Denny
4 months ago
Totally agree, A, D, & I make sense!
BR
Brice
4 months ago
Wait, are we sure about C? Seems off.
SH
Shizue
6 months ago
I think B is actually the right answer.
TO
Torie
6 months ago
Looks like A, D, & I are the critical ones!
GI
Gilma
6 months ago
I’m confused about whether A, B, F, and J could be the critical path. I need to double-check the dependencies again.
NA
Nada
7 months ago
I’m leaning towards option B, A, C, E, and H, but I feel like I might be mixing up some of the activities.
ER
Ernie
7 months ago
I remember practicing a similar question where we had to identify the critical path, and I think it was more about the dependencies than just the activities listed.
QU
Quentin
7 months ago
I think the critical path includes A, D, and I, but I'm not entirely sure about I being there.