AACE International AACE-PSP Exam - Topic 4 Question 35 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 35
Topic #: 4
[All AACE-PSP Questions]

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Lezlie
2 months ago
Just a fact: SPI < 1 = behind schedule.
upvoted 0 times
...
Solange
3 months ago
Agreed, less than one means delays.
upvoted 0 times
...
Janessa
3 months ago
Wait, are we sure about that?
upvoted 0 times
...
Kelvin
3 months ago
Yup, that's how earned value works!
upvoted 0 times
...
Meghann
3 months ago
Definitely behind schedule.
upvoted 0 times
...
Gilberto
3 months ago
I definitely recall that a SPI under one indicates we're not on track, so I believe it’s option D for behind schedule.
upvoted 0 times
...
Marlon
4 months ago
I’m a bit uncertain about this one. I thought a lower index might mean we’re ahead, but that doesn’t seem right now.
upvoted 0 times
...
Cristy
4 months ago
I remember practicing a similar question, and I think it was about being behind schedule too. So, I would go with option D.
upvoted 0 times
...
Avery
4 months ago
I think a schedule performance index less than one means the project is behind schedule, but I'm not completely sure.
upvoted 0 times
...
Whitley
4 months ago
I'm pretty confident on this one. The schedule performance index is a measure of how the project is performing compared to the baseline schedule. If the index is less than 1, that means the project is lagging behind, so the answer is D.
upvoted 0 times
...
Rose
4 months ago
Okay, I got this. A schedule performance index less than 1 indicates the project is not meeting its planned schedule, so the correct answer must be D - behind schedule.
upvoted 0 times
...
Casie
5 months ago
I'm a bit unsure about this one. I know the schedule performance index is related to project progress, but I can't quite remember if a value less than 1 means ahead or behind schedule. Let me think this through carefully.
upvoted 0 times
...
Katie
5 months ago
Hmm, this one seems straightforward. A schedule performance index less than 1 means the project is behind schedule, so the answer must be D.
upvoted 0 times
...
Elina
9 months ago
I believe the correct answer is D) behind schedule because a schedule performance index less than one indicates the project is not meeting the planned schedule.
upvoted 0 times
...
Pansy
9 months ago
I'm not sure, but I think it's either A) ahead of schedule or D) behind schedule.
upvoted 0 times
...
Ceola
9 months ago
Hmm, let me think... Behind schedule, that's gotta be it. Unless the project manager has been slipping me some funny brownies, that is.
upvoted 0 times
Chaya
8 months ago
D) behind schedule
upvoted 0 times
...
Mica
8 months ago
C) complete
upvoted 0 times
...
Willie
9 months ago
B) on schedule
upvoted 0 times
...
Eleni
9 months ago
A) ahead of schedule
upvoted 0 times
...
...
Lauran
9 months ago
I agree with Malika, a schedule performance index of less than one means the project is behind schedule.
upvoted 0 times
...
Malika
10 months ago
I think the answer is D) behind schedule.
upvoted 0 times
...
Alysa
10 months ago
I'm going with D. Behind schedule. Might as well just punch in 'D' and call it a day.
upvoted 0 times
...
Lisandra
10 months ago
Clearly, a schedule performance index of less than one means the project is behind schedule. Duh!
upvoted 0 times
Afton
8 months ago
B) on schedule
upvoted 0 times
...
Lillian
8 months ago
Exactly, a schedule performance index of less than one indicates the project is behind schedule.
upvoted 0 times
...
Andra
10 months ago
D) behind schedule
upvoted 0 times
...
...