AACE International AACE-PSP Exam - Topic 4 Question 35 Discussion

Posted by Dannie on May 03, 2025 at 08:22 PM

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Suggested Answer: A

Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
27 comments · newest first
LE
Lezlie 10 months ago
Just a fact: SPI < 1 = behind schedule.
SO
Solange 10 months ago
Agreed, less than one means delays.
JA
Janessa 11 months ago
Wait, are we sure about that?
KE
Kelvin 11 months ago
Yup, that's how earned value works!
ME
Meghann 11 months ago
Definitely behind schedule.
GI
Gilberto 11 months ago
I definitely recall that a SPI under one indicates we're not on track, so I believe it’s option D for behind schedule.
MA
Marlon 12 months ago
I’m a bit uncertain about this one. I thought a lower index might mean we’re ahead, but that doesn’t seem right now.
CR
Cristy 12 months ago
I remember practicing a similar question, and I think it was about being behind schedule too. So, I would go with option D.
AV
Avery 1 year ago
I think a schedule performance index less than one means the project is behind schedule, but I'm not completely sure.
WH
Whitley 1 year ago
I'm pretty confident on this one. The schedule performance index is a measure of how the project is performing compared to the baseline schedule. If the index is less than 1, that means the project is lagging behind, so the answer is D.
RO
Rose 1 year ago
Okay, I got this. A schedule performance index less than 1 indicates the project is not meeting its planned schedule, so the correct answer must be D - behind schedule.
CA
Casie 1 year ago
I'm a bit unsure about this one. I know the schedule performance index is related to project progress, but I can't quite remember if a value less than 1 means ahead or behind schedule. Let me think this through carefully.
KA
Katie 1 year ago
Hmm, this one seems straightforward. A schedule performance index less than 1 means the project is behind schedule, so the answer must be D.
EL
Elina 1 year ago
I believe the correct answer is D) behind schedule because a schedule performance index less than one indicates the project is not meeting the planned schedule.
PA
Pansy 1 year ago
I'm not sure, but I think it's either A) ahead of schedule or D) behind schedule.
CE
Ceola 1 year ago
Hmm, let me think... Behind schedule, that's gotta be it. Unless the project manager has been slipping me some funny brownies, that is.
CH
Chaya 1 year ago
↳ replying to Ceola
D) behind schedule
MI
Mica 1 year ago
↳ replying to Ceola
C) complete
WI
Willie 1 year ago
↳ replying to Ceola
B) on schedule
EL
Eleni 1 year ago
↳ replying to Ceola
A) ahead of schedule
LA
Lauran 1 year ago
I agree with Malika, a schedule performance index of less than one means the project is behind schedule.
MA
Malika 1 year ago
I think the answer is D) behind schedule.
AL
Alysa 1 year ago
I'm going with D. Behind schedule. Might as well just punch in 'D' and call it a day.
LI
Lisandra 1 year ago
Clearly, a schedule performance index of less than one means the project is behind schedule. Duh!
AF
Afton 1 year ago
↳ replying to Lisandra
B) on schedule
LI
Lillian 1 year ago
↳ replying to Lisandra
Exactly, a schedule performance index of less than one indicates the project is behind schedule.
AN
Andra 1 year ago
↳ replying to Lisandra
D) behind schedule
0/2000 characters

Save Cancel