Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 30 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 30
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Chantay
3 months ago
Alright, I've got my calculator and a fresh cup of coffee. Time to crunch the numbers and see what the correct answer is.
upvoted 0 times
Marvel
2 months ago
C) 45
upvoted 0 times
...
Kirk
2 months ago
B) 30
upvoted 0 times
...
Marcelle
2 months ago
A) 35
upvoted 0 times
...
...
Jodi
4 months ago
Wait, reducing the duration of Activity A? That's like trying to lose weight by cutting off your foot. Let's hope the exam isn't full of these kinds of logic puzzles!
upvoted 0 times
Nakisha
2 months ago
I agree, let's hope the exam is more straightforward than this question.
upvoted 0 times
...
Nicolette
2 months ago
I think it's B) 30. That's my best guess.
upvoted 0 times
...
Maddie
2 months ago
I know, right? It seems like a strange way to calculate completion dates.
upvoted 0 times
...
...
Eun
4 months ago
Okay, let's see. If Activity A is shortened, that could push the completion of Activity C forward. I'll try to work this out step-by-step.
upvoted 0 times
Aaron
2 months ago
So, it seems like the completion of Activity C is directly affected by the duration of Activity A.
upvoted 0 times
...
Kristeen
2 months ago
If Activity A is reduced by ten days, then Activity C would complete on day 30.
upvoted 0 times
...
Selma
2 months ago
But what if it's reduced by ten days instead?
upvoted 0 times
...
Freeman
3 months ago
I think if Activity A is reduced by five days, Activity C would complete on day 35.
upvoted 0 times
...
...
Carey
4 months ago
I'm not sure, but I think the answer is B) 30 as well. It makes sense logically.
upvoted 0 times
...
Lazaro
4 months ago
I agree with Adaline, because if Activity A is reduced by 5 days, it would finish on Day 30.
upvoted 0 times
...
Kerry
4 months ago
Hmm, reducing the duration of Activity A seems like it would affect the entire project timeline. I'll have to think this through carefully.
upvoted 0 times
Daron
2 months ago
D) 40
upvoted 0 times
...
Fannie
2 months ago
C) 45
upvoted 0 times
...
Tabetha
2 months ago
B) 30
upvoted 0 times
...
Clorinda
2 months ago
A) 35
upvoted 0 times
...
...
Adaline
4 months ago
I think the answer is B) 30.
upvoted 0 times
...

Save Cancel