New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 4 Question 30 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 30
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Ashley
3 months ago
Yeah, 40 days makes sense with the reduction!
upvoted 0 times
...
Dominga
3 months ago
Wait, reducing by five days? That changes everything!
upvoted 0 times
...
Ashlyn
3 months ago
Not so sure about that, could be 30 days too.
upvoted 0 times
...
Lisandra
4 months ago
Definitely 35 days!
upvoted 0 times
...
Galen
4 months ago
I think it would be 40 days.
upvoted 0 times
...
Lashonda
4 months ago
I'm not entirely confident, but I think the answer might be 40 days? I just remember that it was one of the options we discussed in class.
upvoted 0 times
...
Kendra
4 months ago
If Activity A is reduced by five days, wouldn't that mean Activity C could finish earlier too? I feel like I need to double-check the dependencies.
upvoted 0 times
...
Nilsa
4 months ago
I think we practiced a similar question where changing one activity's duration shifted the completion date of others. I just can't recall the exact numbers.
upvoted 0 times
...
Glory
5 months ago
I remember something about how reducing the duration of one activity can affect the overall timeline, but I'm not sure how that applies here.
upvoted 0 times
...
Queenie
5 months ago
Wait, I'm a bit confused. Reducing the duration of Activity A doesn't necessarily mean Activity C will complete 5 days earlier. There could be other factors at play that affect the timeline. I better re-read the question and think it through step-by-step.
upvoted 0 times
...
Yong
5 months ago
I've got this! If Activity A's duration is reduced by 5 days, that means Activity C's completion date would be 5 days earlier. So the answer has to be 45 - 5 = 40 days.
upvoted 0 times
...
Providencia
5 months ago
Hmm, this seems like a tricky one. I'll need to map out the dependencies between the activities and how changing the duration of one impacts the others. Gotta be careful with the logic here.
upvoted 0 times
...
Yuriko
5 months ago
Okay, let me think this through. If the duration of Activity A is reduced by 5 days, that would impact the start and end dates of the other activities. I'll need to re-calculate the timeline to determine when Activity C would complete.
upvoted 0 times
...
Chantay
10 months ago
Alright, I've got my calculator and a fresh cup of coffee. Time to crunch the numbers and see what the correct answer is.
upvoted 0 times
Marvel
8 months ago
C) 45
upvoted 0 times
...
Kirk
9 months ago
B) 30
upvoted 0 times
...
Marcelle
9 months ago
A) 35
upvoted 0 times
...
...
Jodi
10 months ago
Wait, reducing the duration of Activity A? That's like trying to lose weight by cutting off your foot. Let's hope the exam isn't full of these kinds of logic puzzles!
upvoted 0 times
Nakisha
9 months ago
I agree, let's hope the exam is more straightforward than this question.
upvoted 0 times
...
Nicolette
9 months ago
I think it's B) 30. That's my best guess.
upvoted 0 times
...
Maddie
9 months ago
I know, right? It seems like a strange way to calculate completion dates.
upvoted 0 times
...
...
Eun
10 months ago
Okay, let's see. If Activity A is shortened, that could push the completion of Activity C forward. I'll try to work this out step-by-step.
upvoted 0 times
Aaron
8 months ago
So, it seems like the completion of Activity C is directly affected by the duration of Activity A.
upvoted 0 times
...
Kristeen
9 months ago
If Activity A is reduced by ten days, then Activity C would complete on day 30.
upvoted 0 times
...
Selma
9 months ago
But what if it's reduced by ten days instead?
upvoted 0 times
...
Freeman
10 months ago
I think if Activity A is reduced by five days, Activity C would complete on day 35.
upvoted 0 times
...
...
Carey
11 months ago
I'm not sure, but I think the answer is B) 30 as well. It makes sense logically.
upvoted 0 times
...
Lazaro
11 months ago
I agree with Adaline, because if Activity A is reduced by 5 days, it would finish on Day 30.
upvoted 0 times
...
Kerry
11 months ago
Hmm, reducing the duration of Activity A seems like it would affect the entire project timeline. I'll have to think this through carefully.
upvoted 0 times
Daron
9 months ago
D) 40
upvoted 0 times
...
Fannie
9 months ago
C) 45
upvoted 0 times
...
Tabetha
9 months ago
B) 30
upvoted 0 times
...
Clorinda
9 months ago
A) 35
upvoted 0 times
...
...
Adaline
11 months ago
I think the answer is B) 30.
upvoted 0 times
...

Save Cancel