Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 30 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 30
Topic #: 4
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity A was reduced by five days?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Carey
5 days ago
I'm not sure, but I think the answer is B) 30 as well. It makes sense logically.
upvoted 0 times
...
Lazaro
7 days ago
I agree with Adaline, because if Activity A is reduced by 5 days, it would finish on Day 30.
upvoted 0 times
...
Kerry
7 days ago
Hmm, reducing the duration of Activity A seems like it would affect the entire project timeline. I'll have to think this through carefully.
upvoted 0 times
...
Adaline
14 days ago
I think the answer is B) 30.
upvoted 0 times
...

Save Cancel