Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 4 Question 2 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 2
Topic #: 4
[All AACE-PSP Questions]

What is the free float for Activity F?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Oliva
4 months ago
I agree with Lynna, 2 months sounds right!
upvoted 0 times
...
Juliana
4 months ago
Wait, how can it be 3 months? That seems off.
upvoted 0 times
...
Magda
4 months ago
I’m pretty sure it’s 1 month.
upvoted 0 times
...
Lorean
5 months ago
Definitely not, it's 0 months!
upvoted 0 times
...
Lynna
5 months ago
I think the free float is 2 months.
upvoted 0 times
...
Pearly
5 months ago
I vaguely recall that free float is often less than or equal to total float. I’m leaning towards 1 month for Activity F, but I’m not entirely confident.
upvoted 0 times
...
Almeta
5 months ago
I’m a bit confused about the difference between free float and total float. I feel like it could be 0 months, but I need to double-check my notes.
upvoted 0 times
...
Andra
5 months ago
I remember a practice question where we had to find the free float, and I think it was related to the total float. Could it be 2 months for Activity F?
upvoted 0 times
...
Alison
6 months ago
I think free float is the amount of time an activity can be delayed without affecting the subsequent activities, but I'm not sure how to calculate it for Activity F.
upvoted 0 times
...
Ronnie
6 months ago
I've got this! Free float is the amount of time an activity can be delayed without affecting the project end date. I'll use the information in the diagram to figure out Activity F's free float.
upvoted 0 times
...
Teddy
6 months ago
This should be straightforward. I just need to look at the start and end times for Activity F and calculate the difference between the latest finish time and the earliest start time.
upvoted 0 times
...
Gracie
6 months ago
Okay, let me think this through step-by-step. I need to find the total float and the total duration of the critical path, then subtract that from the duration of Activity F.
upvoted 0 times
...
Tyisha
6 months ago
Hmm, this looks like a critical path question. I'll need to carefully analyze the activity dependencies and durations to determine the free float for Activity F.
upvoted 0 times
...
Leonie
6 months ago
I'm a bit confused by the question. Can someone explain what "free float" means in the context of this project schedule?
upvoted 0 times
...
Vallie
6 months ago
This looks like a pretty straightforward Ansible playbook to set up a development web environment. I think I can handle this one.
upvoted 0 times
...
Gennie
6 months ago
I'm a bit uncertain about the Shared Resources pattern. I think it helps with resource management, but I'm not entirely sure how it relates to the current problem.
upvoted 0 times
...
Francine
6 months ago
Hmm, I'm a bit confused about the stock level boundaries. Does "at least one" mean that as long as any one configuration is in stock, the order can be processed? Or does it mean that all the selected options need to be in stock? I'd want to clarify that before designing the test cases.
upvoted 0 times
...
Anissa
2 years ago
I agree with Silva, it makes sense for it to be 1 month.
upvoted 0 times
...
Joaquin
2 years ago
I think it's 3 months because of the dependencies.
upvoted 0 times
...
Stephanie
2 years ago
I remember studying that it is actually 0 months.
upvoted 0 times
...
Alpha
2 years ago
I disagree, I believe it is 2 months.
upvoted 0 times
...
Silva
2 years ago
I think the free float for Activity F is 1 month.
upvoted 0 times
...
Paulene
2 years ago
I see where you're coming from, Ariel. But I still think it's 2 months.
upvoted 0 times
...
Ariel
2 years ago
I'm pretty sure it's 0 months, based on the diagram.
upvoted 0 times
...
Blondell
2 years ago
I disagree, I believe it is 1 month.
upvoted 0 times
...
Flo
2 years ago
I think the free float for Activity F is 2 months.
upvoted 0 times
...

Save Cancel