Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 15 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 15
Topic #: 4
[All AACE-PSP Questions]

Determine the correct formula and date for the late finish for Activity 9004.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Maurine
5 days ago
Hmm, I'm not convinced. Shouldn't the late finish be the late start plus the lag? I think B is the correct answer.
upvoted 0 times
...
Arlie
9 days ago
I'm pretty sure the answer is D, but I'm not 100% sure about the formula. The late finish should be the late start minus the lag, minus 1 day, right?
upvoted 0 times
...
Mabel
13 days ago
But the rationale behind option B makes more sense to me, as it accounts for the lag time and gives the correct date.
upvoted 0 times
...
Coleen
14 days ago
I disagree, I believe the correct formula is D) LS.10002 - Lag.7 - l day -> 11-20-03.
upvoted 0 times
...
Mabel
16 days ago
I think the correct formula is B) LS.10002^ Lag.7 + i day -> 11-20-03.
upvoted 0 times
...

Save Cancel