Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 3 Question 8 Discussion

Actual exam question for AACE International's Planning & Scheduling Professional (PSP) Exam exam
Question #: 8
Topic #: 3
[All Planning & Scheduling Professional (PSP) Exam Questions]

Which of the following is NOT true?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Laquanda
8 days ago
Agreed. Option B is a solid one. Now, option C... Multiple calendars can affect the total float calculation. That makes sense to me.
upvoted 0 times
...
Leonard
10 days ago
You make a good point. Option A seems a bit shaky. Let's move on to option B. Constraints can definitely interfere with the longest path calculation. That's a core concept in critical path analysis.
upvoted 0 times
...
Beatriz
11 days ago
Hmm, I'm not so sure about that. Doesn't the remaining duration have to be less than or equal to the original duration? Otherwise, how would we be able to complete the project on time?
upvoted 0 times
...
Margurite
12 days ago
Okay, let's start with option A. I think remaining durations can exceed original durations, right? That seems like a pretty straightforward concept.
upvoted 0 times
...
Arminda
14 days ago
Yeah, I agree. The wording is a bit convoluted. Let's go through this step by step and see if we can figure it out.
upvoted 0 times
...
Carlota
16 days ago
This question seems a bit tricky. I'm not sure if I fully understand the implications of each answer option.
upvoted 0 times
...

Save Cancel