Who will receive the most benefit from a master schedule of the Spring Highway project?
Suggested Answer: D
Get Premium AACE-PSP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
SDOT, as the project owner or primary stakeholder, benefits most from a master schedule as it provides an overview of progress, resource allocation, and critical path analysis for the entire project.
Contractors (e.g., BILCO) may rely on more detailed schedules specific to their scope rather than the overall master schedule.
Reference: PSP Study Guide, Section 2.4.8 -- Management Summary, which explains how master schedules are valuable to owners and stakeholders for overall project oversight.
3 comments · newest first
FA
Fairy
3 days ago
I'm leaning towards ALPHA, but I can't recall their specific role in the project.
AS
Ashlyn
8 days ago
I remember a similar question where the contractor benefited the most, so maybe it's GOUGE, Inc this time?
TI
Tina
13 days ago
I think it might be SDOT since they oversee the project, but I'm not entirely sure.