I remember practicing a similar question where we had to calculate the late finish based on the LS of the previous activity. I think it was always minus a day.
I'm a bit confused by this question. I'm not sure how the late start of 6003 is related to the late finish of 6002. I'll need to double-check my understanding of the project management concepts involved here.
I've got this! The late finish of Activity 6002 is the late start of Activity 6003 minus 1 day, which equals 09 Mar 2023. Option C is the correct answer.
Hmm, this is a tricky one. I'm not entirely sure which formula to use here. I'll need to carefully review the options and make sure I understand the relationship between Activities 6002 and 6003.
Okay, let me think this through. I need to determine the correct formula and date for the late finish of Activity 6002. The options mention the late start (LS) of Activity 6003, so I'll need to use that information to calculate the late finish of 6002.
upvoted 0 times
...
Log in to Pass4Success
Sign in:
Report Comment
Is the comment made by USERNAME spam or abusive?
Commenting
In order to participate in the comments you need to be logged-in.
You can sign-up or
login
Therese
2 months agoLizbeth
3 months agoBobbye
3 months agoRex
3 months agoWinfred
3 months agoLaurel
3 months agoTresa
4 months agoAlyssa
4 months agoValentin
4 months agoBarrett
4 months agoCherelle
4 months agoBettina
5 months agoGerald
5 months ago