AACE International Exam AACE-PSP Topic 3 Question 20 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 20
Topic #: 3
[All AACE-PSP Questions]

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Janine
8 days ago
But wouldn't D) The cost estimate for the plant also be important in determining work activity durations?
upvoted 0 times
...
Odette
10 days ago
I agree with Cheryll. Using past project data can help us estimate work activity durations more accurately.
upvoted 0 times
...
Cheryll
13 days ago
I think B) Critical path schedules prepared by you for similar completed projects would be most valuable.
upvoted 0 times
...