AACE International Exam AACE-PSP Topic 3 Question 20 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 20
Topic #: 3
[All AACE-PSP Questions]

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Viva
13 days ago
Hmm, let me see... A, B, C, or D? Eenie, meenie, minie, moe, catch a tiger by the toe... Oops, sorry, wrong game. I'm going with C, the Petrochemical handbook. Sounds like the most reliable source to me.
upvoted 0 times
...
Carey
15 days ago
The cost estimate from the estimating department? Really? That's like asking the accounting team to design the plant. Option C is the clear winner.
upvoted 0 times
...
Percy
18 days ago
I'm going with B. Using your own previous experience with similar projects is the way to go. You know the real-world timelines better than any industry publication.
upvoted 0 times
...
Abel
1 months ago
The Petrochemical Industry New Plant Task Duration Handbook is the obvious choice here. It's a specialized resource that would provide the most accurate and relevant information for determining activity durations.
upvoted 0 times
Tyisha
2 days ago
C) The Petrochemical Industry New Plant Task Duration Handbook.
upvoted 0 times
...
Sharee
7 days ago
B) Critical path schedules prepared by you for similar completed projects.
upvoted 0 times
...
Alease
13 days ago
A) Industry publications.
upvoted 0 times
...
...
Janine
2 months ago
But wouldn't D) The cost estimate for the plant also be important in determining work activity durations?
upvoted 0 times
...
Odette
2 months ago
I agree with Cheryll. Using past project data can help us estimate work activity durations more accurately.
upvoted 0 times
...
Cheryll
2 months ago
I think B) Critical path schedules prepared by you for similar completed projects would be most valuable.
upvoted 0 times
...