AACE International Exam AACE-PSP Topic 3 Question 16 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 16
Topic #: 3
[All AACE-PSP Questions]

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Avery
1 months ago
Haha, rock fill by 100,000 cubic meters? Sounds like someone's been playing Minecraft a little too much. But seriously, I'm going with D) 1000 and 6001. Keeps it simple, you know?
upvoted 0 times
Lazaro
19 days ago
I agree, D) 1000 and 6001 seems like the most logical choice.
upvoted 0 times
...
Rolande
21 days ago
Yeah, I think so too. Let's go with that.
upvoted 0 times
...
Paris
23 days ago
I agree, D) 1000 and 6001 seems like the most logical choice.
upvoted 0 times
...
...
Page
1 months ago
This is a tricky one. I'm picturing a construction site with a giant rock-filled pit, and the project manager's like, 'Yeah, let's just add 100,000 cubic meters. No biggie.' Gotta go with D) 1000 and 6001.
upvoted 0 times
...
Yuonne
1 months ago
Wait, what? 9001 and 6002 and 6002? That's like a triple-decker sandwich of activities. I'll have to pass on that one. B) 1000, 1001, and 6001 seems more reasonable.
upvoted 0 times
Pearlie
7 days ago
Definitely, it makes more sense than the triple-decker sandwich of activities.
upvoted 0 times
...
Hollis
20 days ago
Yeah, that seems like the most logical option.
upvoted 0 times
...
Enola
29 days ago
I think B) 1000, 1001, and 6001 is the right choice.
upvoted 0 times
...
...
Graciela
1 months ago
Hmm, let's see. The change order impacted Activity 6001, so that's a given. But what about the other activities? Looks like D) 1000 and 6001 is the way to go. Simple and straightforward.
upvoted 0 times
...
Daren
2 months ago
I'm not sure. I think it could also be D) 1000 and 6001.
upvoted 0 times
...
Stanton
2 months ago
I agree with Kizzy. The scope change would impact those activities.
upvoted 0 times
...
Kizzy
2 months ago
I think the answer is B) 1000, 1001, and 6001.
upvoted 0 times
...
Laila
2 months ago
I'm not sure about the answer. Can someone explain the rationale behind it?
upvoted 0 times
...
Sherly
2 months ago
I agree with Pete. The scope change would impact those activities.
upvoted 0 times
...
Pete
2 months ago
I think the answer is B) 1000, 1001, and 6001.
upvoted 0 times
...