What day would Activity C complete if the duration of Activity B was reduced to zero?
A) 50
B) 20
C) 30
D) 40

AACE International AACE-PSP Exam - Topic 2 Question 52 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 52
Topic #: 2
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity B was reduced to zero?

Show Suggested Answer Hide Answer
Suggested Answer: A

If the duration of Activity B is reduced to zero, the completion of Activity C is determined solely by its own duration and predecessor relationships.

Without knowing the explicit network logic, it is inferred that reducing Activity B to zero does not affect Activity C's finish on Day 50, as its relationship with other activities remains intact.

Reference: PSP Study Guide, Section 2.2.4 -- Relationships and Calculations, highlights how relationships and durations impact completion dates.