Halloween Special 2026! Get Up to 25% OFF Practice Questions! Limited Time - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 2 Question 52 Discussion

Posted by Haydee on May 26, 2026 at 02:20 PM

What day would Activity C complete if the duration of Activity B was reduced to zero?

Suggested Answer: A

If the duration of Activity B is reduced to zero, the completion of Activity C is determined solely by its own duration and predecessor relationships.

Without knowing the explicit network logic, it is inferred that reducing Activity B to zero does not affect Activity C's finish on Day 50, as its relationship with other activities remains intact.

Reference: PSP Study Guide, Section 2.2.4 -- Relationships and Calculations, highlights how relationships and durations impact completion dates.


Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
24 comments · newest first
CR
Cristal 1 day ago
Good idea!
KR
Kristofer 6 days ago
Let’s calculate again.
MI
Michell 12 days ago
I’m still unsure.
FI
Filiberto 17 days ago
So, C or D?
GA
Galen 22 days ago
I might change to C too.
CR
Cruz 27 days ago
C makes sense with reduced time.
SH
Sheron 1 month ago
I vote for C.
EU
Eulah 1 month ago
But it adds up correctly.
CR
Cristal 1 month ago
A seems too late for me.
EU
Eulah 2 months ago
I believe it's A.
KR
Kristofer 2 months ago
If B is zero, C finishes earlier.
GA
Galen 2 months ago
Why D?
KR
Kristofer 2 months ago
I lean towards option D.
MI
Michell 2 months ago
I feel confused about the durations.
FI
Filiberto 2 months ago
I think it's tricky.
RE
Reta 3 months ago
I thought it would be 50, but now I'm not so sure!
JU
Julieta 3 months ago
I agree, 40 makes the most sense here.
SH
Shenika 3 months ago
Wait, how can Activity B be zero? That seems off.
GA
Gabriele 3 months ago
Definitely not, it's 40 for sure.
EV
Eveline 3 months ago
I think it would be 30.
ET
Ettie 3 months ago
I really can't remember how reducing durations impacts the schedule. I guess it could be any of these options, but I'm leaning towards 20.
FA
Fatima 4 months ago
I feel like I might have seen something similar where the dependencies played a big role. Is it possible that Activity C could still finish on day 40?
CA
Caprice 4 months ago
I remember a practice question where reducing a task's duration changed the finish date significantly. Could it be 30 days?
SH
Sherell 4 months ago
I think if Activity B has zero duration, it might push Activity C to finish earlier, but I'm not sure how that affects the overall timeline.
0/2000 characters

Save Cancel