AACE International AACE-PSP Exam - Topic 2 Question 52 Discussion

What day would Activity C complete if the duration of Activity B was reduced to zero?
A) 50
B) 20
C) 30
D) 40

AACE International AACE-PSP Exam - Topic 2 Question 52 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 52
Topic #: 2
[All AACE-PSP Questions]

What day would Activity C complete if the duration of Activity B was reduced to zero?

Show Suggested Answer Hide Answer
Suggested Answer: A

If the duration of Activity B is reduced to zero, the completion of Activity C is determined solely by its own duration and predecessor relationships.

Without knowing the explicit network logic, it is inferred that reducing Activity B to zero does not affect Activity C's finish on Day 50, as its relationship with other activities remains intact.

Reference: PSP Study Guide, Section 2.2.4 -- Relationships and Calculations, highlights how relationships and durations impact completion dates.


Contribute your Thoughts:

0/2000 characters
Kristofer
4 days ago
I lean towards option D.
upvoted 0 times
...
Michell
9 days ago
I feel confused about the durations.
upvoted 0 times
...
Filiberto
15 days ago
I think it's tricky.
upvoted 0 times
...
Reta
20 days ago
I thought it would be 50, but now I'm not so sure!
upvoted 0 times
...
Julieta
25 days ago
I agree, 40 makes the most sense here.
upvoted 0 times
...
Shenika
1 month ago
Wait, how can Activity B be zero? That seems off.
upvoted 0 times
...
Gabriele
1 month ago
Definitely not, it's 40 for sure.
upvoted 0 times
...
Eveline
1 month ago
I think it would be 30.
upvoted 0 times
...
Ettie
2 months ago
I really can't remember how reducing durations impacts the schedule. I guess it could be any of these options, but I'm leaning towards 20.
upvoted 0 times
...
Fatima
2 months ago
I feel like I might have seen something similar where the dependencies played a big role. Is it possible that Activity C could still finish on day 40?
upvoted 0 times
...
Caprice
2 months ago
I remember a practice question where reducing a task's duration changed the finish date significantly. Could it be 30 days?
upvoted 0 times
...
Sherell
2 months ago
I think if Activity B has zero duration, it might push Activity C to finish earlier, but I'm not sure how that affects the overall timeline.
upvoted 0 times
...

Save Cancel