AACE International AACE-PSP Exam - Topic 2 Question 47 Discussion

What is the free float for Activity F?
B) 0 months.
A) 3 months.
C) 1 months.
D) 2 month.

AACE International AACE-PSP Exam - Topic 2 Question 47 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 47
Topic #: 2
[All AACE-PSP Questions]

What is the free float for Activity F?

Show Suggested Answer Hide Answer
Suggested Answer: B

Understand Free Float: Free float is the time an activity can be delayed without delaying the start of its immediate successor.

Review Activity F in the Diagram:

Activity F has a successor that starts later, providing room for 2 months of free float.

Cross-Verification:

Option A: Incorrect. Overestimates the float.

Option B: Incorrect. No float is incorrect for F.

Option C: Incorrect. 1 month is insufficient.

Option D: Correct. Matches the calculated free float for Activity F.


Contribute your Thoughts:

0/2000 characters
Veronica
4 hours ago
Wait, is it really 2 months? That seems off.
upvoted 0 times
...
Lenny
2 months ago
Not sure about that, could be B) 0 months.
upvoted 0 times
...
Wendell
2 months ago
Definitely A) 3 months!
upvoted 0 times
...
Shayne
2 months ago
I think it's 0 months.
upvoted 0 times
...
Dean
2 months ago
I agree, 2 months makes the most sense here.
upvoted 0 times
...
Delfina
2 months ago
Wait, how can it be 3 months? That seems too long!
upvoted 0 times
...
Georgene
2 months ago
I’m pretty sure it’s 1 month.
upvoted 0 times
...
Bev
3 months ago
Definitely not 0 months, that seems off.
upvoted 0 times
...
Vi
3 months ago
I think the free float is 2 months.
upvoted 0 times
...
Arlene
3 months ago
I definitely recall that free float can be tricky. I think it might be 3 months, but I need to double-check my notes on that.
upvoted 0 times
...
Junita
3 months ago
I’m really uncertain about this one. I thought free float was always more than 0, but I guess it could be 0 months for Activity F.
upvoted 0 times
...
Gwenn
3 months ago
I remember practicing a similar question where we had to calculate float. I feel like the answer might be 0 months, but I could be wrong.
upvoted 0 times
...
Joesph
3 months ago
I think free float is the amount of time an activity can be delayed without affecting the subsequent activities. I’m not sure if it’s 1 or 2 months for Activity F.
upvoted 0 times
...