Which of the following will always describe the critical path? The path with
Suggested Answer: B
Get Premium AACE-PSP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
26 comments · newest first
CH
Chantell
10 months ago
I thought the critical path was about minimizing time, not maximizing it!
RO
Rosio
10 months ago
Wait, negative float? That sounds off.
DE
Delfina
10 months ago
I agree, zero float means it's critical too.
RO
Rosendo
11 months ago
A and B are both true for the critical path.
JE
Jerry
11 months ago
A is definitely correct, longest duration!
KA
Kaitlyn
11 months ago
Negative float sounds familiar, but I don’t think that’s what defines the critical path. I might need to double-check my notes.
KE
Keith
11 months ago
I practiced a similar question where the critical path was described as having the longest duration, so I’m leaning towards option A.
MA
Magda
12 months ago
I remember something about zero float being important for the critical path, but I can't recall if it was the defining characteristic.
CO
Colby
12 months ago
I think the critical path is the one with the longest duration, but I'm not completely sure if that's the only factor.
MA
Marya
1 year ago
I think the key here is to focus on the duration of the path, not just the float. The critical path is the one with the longest duration, so A is the correct answer.
WE
Weldon
1 year ago
Wait, I thought the critical path was the one with negative float. That's what we covered in class, right? I'm going to have to double-check my notes on this.
CH
Cherry
1 year ago
Okay, I remember learning that the critical path has no float, so that means it's option B. The path with zero float is always the critical path.
AM
Amie
1 year ago
Hmm, I'm a bit confused here. I thought the critical path was the one with zero float, but now I'm not so sure. Let me think this through again.
DY
Dylan
1 year ago
This one seems pretty straightforward. The critical path is the longest duration through the network, so I'm going with option A.
JO
Jonelle
1 year ago
The critical path is the one with the longest duration and zero float. That's option B, easy peasy.
DO
Dominga
1 year ago
I think negative float indicates a delay, so it's not the critical path.
VI
Vilma
1 year ago
Haha, D is a bit of a trick question, isn't it? The critical path is definitely the longest duration, not the shortest. B is the way to go.
FA
Fallon
1 year ago
But isn't it interesting how D looks tempting?
PH
Phung
1 year ago
I agree, A is the best answer. Longest duration is key.
PE
Peggie
1 year ago
Definitely! Tricks can be confusing, but A is clear.
VA
Valentine
1 year ago
But what about negative float? Could that also describe the critical path?
AY
Ayesha
1 year ago
I believe it's the path with zero float.
KI
Kirk
1 year ago
Hmm, I'm torn between B and C. The critical path has to have zero or negative float, right? I'll go with C just to be different.
HY
Hyman
1 year ago
I think the answer is B. The critical path has zero float, meaning no slack time. It's the longest duration, but that's not the only defining feature.
NI
Nicolette
1 year ago
I think the answer is B. The critical path has zero float, meaning no slack time.
VA
Valentine
1 year ago
I think the critical path is the one with the longest duration.