AACE International AACE-PSP Exam - Topic 2 Question 39 Discussion

Which of the following will always describe the critical path? The path with
B) Zero float.
A) The longest duration through the network.
C) Negative float.
D) The shortest duration and negative float.

AACE International AACE-PSP Exam - Topic 2 Question 39 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 39
Topic #: 2
[All AACE-PSP Questions]

Which of the following will always describe the critical path? The path with

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Chantell
8 months ago
I thought the critical path was about minimizing time, not maximizing it!
upvoted 0 times
...
Rosio
8 months ago
Wait, negative float? That sounds off.
upvoted 0 times
...
Delfina
8 months ago
I agree, zero float means it's critical too.
upvoted 0 times
...
Rosendo
9 months ago
A and B are both true for the critical path.
upvoted 0 times
...
Jerry
9 months ago
A is definitely correct, longest duration!
upvoted 0 times
...
Kaitlyn
9 months ago
Negative float sounds familiar, but I don’t think that’s what defines the critical path. I might need to double-check my notes.
upvoted 0 times
...
Keith
9 months ago
I practiced a similar question where the critical path was described as having the longest duration, so I’m leaning towards option A.
upvoted 0 times
...
Magda
10 months ago
I remember something about zero float being important for the critical path, but I can't recall if it was the defining characteristic.
upvoted 0 times
...
Colby
10 months ago
I think the critical path is the one with the longest duration, but I'm not completely sure if that's the only factor.
upvoted 0 times
...
Marya
10 months ago
I think the key here is to focus on the duration of the path, not just the float. The critical path is the one with the longest duration, so A is the correct answer.
upvoted 0 times
...
Weldon
10 months ago
Wait, I thought the critical path was the one with negative float. That's what we covered in class, right? I'm going to have to double-check my notes on this.
upvoted 0 times
...
Cherry
10 months ago
Okay, I remember learning that the critical path has no float, so that means it's option B. The path with zero float is always the critical path.
upvoted 0 times
...
Amie
11 months ago
Hmm, I'm a bit confused here. I thought the critical path was the one with zero float, but now I'm not so sure. Let me think this through again.
upvoted 0 times
...
Dylan
11 months ago
This one seems pretty straightforward. The critical path is the longest duration through the network, so I'm going with option A.
upvoted 0 times
...
Jonelle
11 months ago
The critical path is the one with the longest duration and zero float. That's option B, easy peasy.
upvoted 0 times
...
Dominga
11 months ago
I think negative float indicates a delay, so it's not the critical path.
upvoted 0 times
...
Vilma
11 months ago
Haha, D is a bit of a trick question, isn't it? The critical path is definitely the longest duration, not the shortest. B is the way to go.
upvoted 0 times
Fallon
11 months ago
But isn't it interesting how D looks tempting?
upvoted 0 times
...
Phung
11 months ago
I agree, A is the best answer. Longest duration is key.
upvoted 0 times
...
Peggie
11 months ago
Definitely! Tricks can be confusing, but A is clear.
upvoted 0 times
...
...
Valentine
11 months ago
But what about negative float? Could that also describe the critical path?
upvoted 0 times
...
Ayesha
1 year ago
I believe it's the path with zero float.
upvoted 0 times
...
Kirk
1 year ago
Hmm, I'm torn between B and C. The critical path has to have zero or negative float, right? I'll go with C just to be different.
upvoted 0 times
...
Hyman
1 year ago
I think the answer is B. The critical path has zero float, meaning no slack time. It's the longest duration, but that's not the only defining feature.
upvoted 0 times
Nicolette
1 year ago
I think the answer is B. The critical path has zero float, meaning no slack time.
upvoted 0 times
...
...
Valentine
1 year ago
I think the critical path is the one with the longest duration.
upvoted 0 times
...