Actual exam question for AACE International's AACE-PSP exam
Question #: 39
Topic #: 2
[All AACE-PSP Questions]

Which of the following will always describe the critical path? The path with

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Chantell
2 months ago
I thought the critical path was about minimizing time, not maximizing it!
upvoted 0 times
...
Rosio
2 months ago
Wait, negative float? That sounds off.
upvoted 0 times
...
Delfina
2 months ago
I agree, zero float means it's critical too.
upvoted 0 times
...
Rosendo
3 months ago
A and B are both true for the critical path.
upvoted 0 times
...
Jerry
3 months ago
A is definitely correct, longest duration!
upvoted 0 times
...
Kaitlyn
3 months ago
Negative float sounds familiar, but I don’t think that’s what defines the critical path. I might need to double-check my notes.
upvoted 0 times
...
Keith
3 months ago
I practiced a similar question where the critical path was described as having the longest duration, so I’m leaning towards option A.
upvoted 0 times
...
Magda
4 months ago
I remember something about zero float being important for the critical path, but I can't recall if it was the defining characteristic.
upvoted 0 times
...
Colby
4 months ago
I think the critical path is the one with the longest duration, but I'm not completely sure if that's the only factor.
upvoted 0 times
...
Marya
4 months ago
I think the key here is to focus on the duration of the path, not just the float. The critical path is the one with the longest duration, so A is the correct answer.
upvoted 0 times
...
Weldon
4 months ago
Wait, I thought the critical path was the one with negative float. That's what we covered in class, right? I'm going to have to double-check my notes on this.
upvoted 0 times
...
Cherry
4 months ago
Okay, I remember learning that the critical path has no float, so that means it's option B. The path with zero float is always the critical path.
upvoted 0 times
...
Amie
5 months ago
Hmm, I'm a bit confused here. I thought the critical path was the one with zero float, but now I'm not so sure. Let me think this through again.
upvoted 0 times
...
Dylan
5 months ago
This one seems pretty straightforward. The critical path is the longest duration through the network, so I'm going with option A.
upvoted 0 times
...
Jonelle
5 months ago
The critical path is the one with the longest duration and zero float. That's option B, easy peasy.
upvoted 0 times
...
Dominga
5 months ago
I think negative float indicates a delay, so it's not the critical path.
upvoted 0 times
...
Vilma
5 months ago
Haha, D is a bit of a trick question, isn't it? The critical path is definitely the longest duration, not the shortest. B is the way to go.
upvoted 0 times
Adela
5 months ago
True! B makes sense too, no float means critical.
upvoted 0 times
...
Fallon
5 months ago
But isn't it interesting how D looks tempting?
upvoted 0 times
...
Phung
5 months ago
I agree, A is the best answer. Longest duration is key.
upvoted 0 times
...
Peggie
5 months ago
Definitely! Tricks can be confusing, but A is clear.
upvoted 0 times
...
...
Valentine
5 months ago
But what about negative float? Could that also describe the critical path?
upvoted 0 times
...
Ayesha
7 months ago
I believe it's the path with zero float.
upvoted 0 times
...
Kirk
7 months ago
Hmm, I'm torn between B and C. The critical path has to have zero or negative float, right? I'll go with C just to be different.
upvoted 0 times
...
Hyman
7 months ago
I think the answer is B. The critical path has zero float, meaning no slack time. It's the longest duration, but that's not the only defining feature.
upvoted 0 times
Nicolette
6 months ago
I think the answer is B. The critical path has zero float, meaning no slack time.
upvoted 0 times
...
...
Valentine
7 months ago
I think the critical path is the one with the longest duration.
upvoted 0 times
...