Posted by Princess on Aug 02, 2025 at 07:31 AM

Which of the following will always describe the critical path? The path with

Suggested Answer: B

Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
26 comments · newest first
CH
Chantell 10 months ago
I thought the critical path was about minimizing time, not maximizing it!
RO
Rosio 10 months ago
Wait, negative float? That sounds off.
DE
Delfina 10 months ago
I agree, zero float means it's critical too.
RO
Rosendo 11 months ago
A and B are both true for the critical path.
JE
Jerry 11 months ago
A is definitely correct, longest duration!
KA
Kaitlyn 11 months ago
Negative float sounds familiar, but I don’t think that’s what defines the critical path. I might need to double-check my notes.
KE
Keith 11 months ago
I practiced a similar question where the critical path was described as having the longest duration, so I’m leaning towards option A.
MA
Magda 12 months ago
I remember something about zero float being important for the critical path, but I can't recall if it was the defining characteristic.
CO
Colby 12 months ago
I think the critical path is the one with the longest duration, but I'm not completely sure if that's the only factor.
MA
Marya 1 year ago
I think the key here is to focus on the duration of the path, not just the float. The critical path is the one with the longest duration, so A is the correct answer.
WE
Weldon 1 year ago
Wait, I thought the critical path was the one with negative float. That's what we covered in class, right? I'm going to have to double-check my notes on this.
CH
Cherry 1 year ago
Okay, I remember learning that the critical path has no float, so that means it's option B. The path with zero float is always the critical path.
AM
Amie 1 year ago
Hmm, I'm a bit confused here. I thought the critical path was the one with zero float, but now I'm not so sure. Let me think this through again.
DY
Dylan 1 year ago
This one seems pretty straightforward. The critical path is the longest duration through the network, so I'm going with option A.
JO
Jonelle 1 year ago
The critical path is the one with the longest duration and zero float. That's option B, easy peasy.
DO
Dominga 1 year ago
I think negative float indicates a delay, so it's not the critical path.
VI
Vilma 1 year ago
Haha, D is a bit of a trick question, isn't it? The critical path is definitely the longest duration, not the shortest. B is the way to go.
FA
Fallon 1 year ago
↳ replying to Vilma
But isn't it interesting how D looks tempting?
PH
Phung 1 year ago
↳ replying to Vilma
I agree, A is the best answer. Longest duration is key.
PE
Peggie 1 year ago
↳ replying to Vilma
Definitely! Tricks can be confusing, but A is clear.
VA
Valentine 1 year ago
But what about negative float? Could that also describe the critical path?
AY
Ayesha 1 year ago
I believe it's the path with zero float.
KI
Kirk 1 year ago
Hmm, I'm torn between B and C. The critical path has to have zero or negative float, right? I'll go with C just to be different.
HY
Hyman 1 year ago
I think the answer is B. The critical path has zero float, meaning no slack time. It's the longest duration, but that's not the only defining feature.
NI
Nicolette 1 year ago
↳ replying to Hyman
I think the answer is B. The critical path has zero float, meaning no slack time.
VA
Valentine 1 year ago
I think the critical path is the one with the longest duration.