Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 2 Question 22 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 22
Topic #: 2
[All AACE-PSP Questions]

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Denny
26 days ago
This is where all those project management classes finally come in handy. Time to put on my thinking cap and get to work!
upvoted 0 times
Rolland
16 days ago
A) 02-19-04
upvoted 0 times
...
...
Percy
1 months ago
Oooh, this is like a real-life project management puzzle. I can practically smell the Gantt charts from here!
upvoted 0 times
Cruz
1 days ago
A) 02-19-04
upvoted 0 times
...
...
Carli
2 months ago
Alright, let's think this through step-by-step. Wouldn't want to end up with the wrong answer and have to retake the whole exam, am I right?
upvoted 0 times
Major
22 days ago
User 2: Right, so if Activity 1001 slipped 10 days and Activity 1002 slipped 35 days, we need to adjust the completion date accordingly.
upvoted 0 times
...
Junita
27 days ago
User 1: Let's start by calculating the original completion date.
upvoted 0 times
...
...
Lina
2 months ago
I'm not sure, but I think it might be 03-20-04. Can someone explain their reasoning?
upvoted 0 times
...
Ardella
2 months ago
Hmm, this is a tricky one. Let's see, 10 days slipped on Activity 1001 and 35 days on Activity 10002. Gotta do some serious number crunching here.
upvoted 0 times
...
Jamal
2 months ago
I agree with Galen, Activity 10002 slipping 35 days will push the completion date to 03-21-04.
upvoted 0 times
...
Galen
2 months ago
I think the revised completion date is 03-21-04.
upvoted 0 times
...

Save Cancel