Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Suggested Answer: C
Get Premium AACE-PSP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
30 comments · newest first
TA
Tabetha
11 months ago
Totally agree, 03-21-04 makes sense!
ED
Edelmira
11 months ago
Really? That seems like a huge delay!
EL
Eleni
11 months ago
I think the revised date is 03-21-04.
RE
Rebecka
12 months ago
Activity 10002 is slipping 35 days too!
CH
Charolette
12 months ago
Activity 1001 is delayed by 10 days.
OR
Oretha
1 year ago
I’m leaning towards option D, but I can’t quite recall how to confirm the revised completion date with the slips. I hope I remember the right formula!
KE
Kelvin
1 year ago
I’m a bit confused about whether the delays overlap or if they just stack. I feel like I’ve seen both types of questions in our review sessions.
KE
Keneth
1 year ago
I think if Activity 1001 slipped 10 days and Activity 10002 slipped 35 days, we just need to add those delays together, right?
LA
Lavonna
1 year ago
I remember we practiced a similar question where we had to adjust for delays, but I’m not sure how to calculate the new completion date with two activities slipping.
DO
Dominque
1 year ago
No problem, I've got this. I'll just add the 10-day and 35-day delays together, then add that to the original completion date to get the revised date.
KI
Kiley
1 year ago
I'm a bit confused about how to approach this. Do I need to look at the durations of the other activities too, or just focus on the two that slipped?
DE
Dean
1 year ago
Hmm, this seems straightforward enough. I'll need to calculate the total delay and add it to the original completion date to get the revised date.
SE
Serita
1 year ago
Okay, let's think this through step-by-step. Activity 1001 slipped 10 days, and Activity 10002 slipped 35 days. I'll need to add those delays to the original completion date to find the revised date.
JI
Jillian
1 year ago
Alright, let me work through this step-by-step. First I'll add up the delays, then I'll add that to the original completion date. Should be a straightforward calculation.
PA
Paola
1 year ago
Definitely iPhone 7. It's a widely used model that's representative of the iOS ecosystem. Testing on that would give me the best sense of how the app would perform for most users.
DE
Denny
1 year ago
This is where all those project management classes finally come in handy. Time to put on my thinking cap and get to work!
SA
Santos
1 year ago
C) 03-11-04
MO
Mozelle
1 year ago
B) 03-21-04
RO
Rolland
1 year ago
A) 02-19-04
PE
Percy
2 years ago
Oooh, this is like a real-life project management puzzle. I can practically smell the Gantt charts from here!
AF
Afton
1 year ago
C) 03-11-04
LA
Lawrence
1 year ago
B) 03-21-04
CR
Cruz
1 year ago
A) 02-19-04
CA
Carli
2 years ago
Alright, let's think this through step-by-step. Wouldn't want to end up with the wrong answer and have to retake the whole exam, am I right?
MA
Major
1 year ago
User 2: Right, so if Activity 1001 slipped 10 days and Activity 1002 slipped 35 days, we need to adjust the completion date accordingly.
JU
Junita
1 year ago
User 1: Let's start by calculating the original completion date.
LI
Lina
2 years ago
I'm not sure, but I think it might be 03-20-04. Can someone explain their reasoning?
AR
Ardella
2 years ago
Hmm, this is a tricky one. Let's see, 10 days slipped on Activity 1001 and 35 days on Activity 10002. Gotta do some serious number crunching here.
JA
Jamal
2 years ago
I agree with Galen, Activity 10002 slipping 35 days will push the completion date to 03-21-04.
GA
Galen
2 years ago
I think the revised completion date is 03-21-04.