Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 2 Question 17 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 17
Topic #: 2
[All AACE-PSP Questions]

Determine the correct formula and date for the late finish for Activity 2002.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Dong
3 days ago
I'm not sure about this one. The late finish date seems to depend on the formula used, so I'll have to double-check my work.
upvoted 0 times
...
Herminia
7 days ago
I'm not sure, but I think option A makes sense because we are subtracting 1 day from LS.2003.
upvoted 0 times
...
Cyril
8 days ago
I agree with Chantell, the late finish date should be 11.06.01.
upvoted 0 times
...
Rebeca
9 days ago
The late finish for Activity 2002 is clearly 10-06-01 using the formula LS.2003 - 1 day. Option B is the correct answer.
upvoted 0 times
...
Chantell
11 days ago
I think the correct formula is LS.2003 - 1 day.
upvoted 0 times
...

Save Cancel