Deal of The Day! Hurry Up, Grab the Special Discount - Save 25%
- Ends In
00:00:00
Coupon code:
SAVE25
X
Welcome to Pass4Success
Login
|
Sign up
-
Free
Preparation Discussions
Mail Us
support@pass4success.com
Location
US
MENU
Home
Popular vendors
Salesforce
Microsoft
Nutanix
Amazon
Google
CompTIA
SAP
VMware
Fortinet
PeopleCert
Eccouncil
HP
Palo Alto Networks
Adobe
ServiceNow
Dell EMC
CheckPoint
Linux Foundation
Close
Discount Deals
New
About
Contact
Login
Sign up
Home
Discussions
AACE International Discussions
Exam AACE-PSP Topic 2 Question 12 Discussion
AACE International Exam AACE-PSP Topic 2 Question 12 Discussion
Actual exam question for AACE International's AACE-PSP exam
Question #: 12
Topic #: 2
[All AACE-PSP Questions]
How could the structural steel drawing delay have been prevented?
A
Add a time buffer at the end of structural steel activities.
B
Allow adequate time for review and resubmittal in the baseline schedule.
C
Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
D
Switch to post-tensioned concrete construction.
Show Suggested Answer
Hide Answer
Suggested Answer:
A
by
Edgar
at
May 18, 2024, 02:19 PM
Limited Time Offer
25%
Off
Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF
Contribute your Thoughts:
Submit
Cancel
Vannessa
11 months ago
Option C is like playing structural steel Tetris. I wouldn't want to be the one responsible for that gamble.
upvoted
0
times
...
Catherin
11 months ago
I'm going with B. Proactive planning is key to avoiding delays in a project like this.
upvoted
0
times
Beckie
10 months ago
C) Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
upvoted
0
times
...
Oretha
10 months ago
C) Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
upvoted
0
times
...
Rossana
10 months ago
I agree with B. Proactive planning is crucial to prevent delays.
upvoted
0
times
...
Isaac
10 months ago
I agree, proactive planning is essential to prevent delays.
upvoted
0
times
...
Rachael
10 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted
0
times
...
France
11 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted
0
times
...
Annice
11 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted
0
times
...
Isadora
11 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted
0
times
...
...
Golda
11 months ago
C is an interesting idea, but it's a risky move. You might end up with a lot of rework if the drawings aren't approved.
upvoted
0
times
...
Martha
11 months ago
D? Really? That's a bit extreme, don't you think? Switching construction methods is a huge undertaking.
upvoted
0
times
...
Matthew
12 months ago
Option B seems like the obvious choice here. You need to plan for that review process upfront.
upvoted
0
times
Ressie
10 months ago
Yeah, planning for review and resubmittal time is crucial in preventing delays.
upvoted
0
times
...
Marica
11 months ago
I agree, adding a time buffer at the end would have helped.
upvoted
0
times
...
Mariann
11 months ago
B) Allow adequate time for review and resubmittal in the baseline schedule.
upvoted
0
times
...
Josphine
11 months ago
Switching to post-tensioned concrete construction could have been a drastic but effective solution.
upvoted
0
times
...
Kattie
11 months ago
A) Add a time buffer at the end of structural steel activities.
upvoted
0
times
...
Devora
11 months ago
I think releasing the structural steel for fabrication concurrent with review of shop drawings would have been more efficient.
upvoted
0
times
...
Rodolfo
11 months ago
I agree, adding a time buffer at the end of structural steel activities could have helped.
upvoted
0
times
...
...
Log in to Pass4Success
×
Sign in:
Forgot my password
Log in
Report Comment
×
Is the comment made by
USERNAME
spam or abusive?
Commenting
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
Save
Cancel
a
Vannessa
11 months agoCatherin
11 months agoBeckie
10 months agoOretha
10 months agoRossana
10 months agoIsaac
10 months agoRachael
10 months agoFrance
11 months agoAnnice
11 months agoIsadora
11 months agoGolda
11 months agoMartha
11 months agoMatthew
12 months agoRessie
10 months agoMarica
11 months agoMariann
11 months agoJosphine
11 months agoKattie
11 months agoDevora
11 months agoRodolfo
11 months ago