Which of the following is NOT a tool or technique used to perform scope planning?

Suggested Answer: B

Scope Planning Tools and Techniques:

Tools for scope planning include methods to define and refine the project scope. These involve cost-benefit analysis, expert judgment, and alternatives identification.

Schedule performance indexing is a performance tracking tool used during execution and is unrelated to scope planning.

PSP Study Guide Reference:

Scope planning methods are detailed in the PSP guide, emphasizing tools like expert judgment, alternatives analysis, and structured decision-making techniques.

Analysis for Selection:

Option A: A common method to analyze the costs and benefits of scope components.

Option B: Incorrect. This is a tracking tool, not a scope planning method.

Option C: Expert judgment is a key technique in defining project scope.

Option D: Alternatives identification supports exploring various approaches to project goals.

Conclusion: The correct answer is B, as schedule performance indexing is not a scope planning tool.


Get Premium AACE-PSP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
24 comments · newest first
TI
Tien 1 day ago
I feel like C is also a good option.
MI
Mirta 6 days ago
B makes sense. Scope planning is different.
ED
Edelmira 12 days ago
Definitely B. It’s more about tracking progress.
MA
Margurite 17 days ago
A is related to benefits, not scope planning.
TR
Truman 22 days ago
I’m leaning towards A. Benefit cost analysis.
GA
Gabriele 27 days ago
I agree, B seems off. Not really about scope.
CA
Casie 1 month ago
I think the answer is B. Schedule performance indexing.
AL
Alex 1 month ago
D is also a valid tool, so it must be B.
DO
Dorcas 1 month ago
I think C is essential. Expert Judgment is always used.
KA
Kathryn 2 months ago
Yeah, B is about performance, not planning.
AL
Alverta 2 months ago
I feel B is not directly related to scope planning.
SO
Solange 2 months ago
A is definitely a tool, but B feels more like a monitoring tool.
VI
Virgie 2 months ago
I’m leaning towards A. Benefit cost analysis.
KA
Kanisha 2 months ago
I agree, B seems off for scope planning.
NA
Narcisa 2 months ago
I think the answer is B. Schedule performance indexing.
SO
Sonia 3 months ago
I’m surprised that people think B is wrong!
PA
Paris 3 months ago
Yup, B is definitely the odd one out here.
YV
Yvonne 3 months ago
Wait, are we sure about that? I thought it was A) Benefit cost analysis.
NO
Novella 3 months ago
Totally agree, that's not really for scope planning!
RA
Rachael 3 months ago
I think it's B) Schedule performance indexing.
IL
Iluminada 3 months ago
I could be wrong, but benefit cost analysis seems more related to project evaluation rather than scope planning.
TR
Tracey 4 months ago
I practiced a similar question where alternatives identification was mentioned as a planning tool, so I’m leaning towards B as the answer.
GR
Gretchen 4 months ago
I'm not entirely sure, but I feel like expert judgment is definitely a tool used in scope planning.
AN
Anika 4 months ago
I think I remember that schedule performance indexing is more about tracking progress than planning scope, so it might be the right answer.