Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
Cost for 2000 Series Activities:
Activity 2001: $150,000.
Activity 2002: $25,000.
Activity 2003: $18,000.
Activity 2004: $96,000.
Total: 150,000+25,000+18,000+96,000=289,000150,000 + 25,000 + 18,000 + 96,000 = 289,000150,000+25,000+18,000+96,000=289,000.
Total Project Cost:
Total cost: $7,308,000 (sum of all activities in 'normal' schedule).
Percentage Contribution:
289,0007,308,0001003.95%frac{289,000}{7,308,000} times 100 approx 3.95%7,308,000289,0001003.95%.
Verification with PSP Guidelines: The PSP Study Guide emphasizes accuracy in percentage-based cost contributions as a critical analysis tool in project cost management (Ref: PSP Study Guide, Chapter 1B: Cost Breakdown Structure).