You discovered that an incorrect quantity of received goods was recorded.
How will you correct the error?
Receipts in Workday record the quantity of goods or services that have arrived against a purchase order line, and these records sometimes contain data entry errors that need correction without disturbing the underlying purchase order. The Official Workday Pro Procure-to-Pay Guide identifies the Create Receipt Adjustment task as the correct tool for correcting an incorrect quantity that was recorded on a previously entered receipt, allowing the quantity to be revised up or down while maintaining an accurate audit trail of receiving activity. Option B is incorrect because editing the purchase order changes the ordered quantity or terms, not the quantity that was actually recorded as received. Option C is incorrect because Return to Supplier represents a physical return of goods back to the supplier and is used when goods need to be sent back, not simply to correct a recording error. Option D is incorrect because closing the PO line for receiving prevents future receipts but does nothing to correct the inaccurate quantity already recorded on the existing receipt.