Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

VMware Exam 3V0-624 Topic 1 Question 1 Discussion

Actual exam question for VMware's 3V0-624 exam
Question #: 1
Topic #: 1
[All 3V0-624 Questions]

A solution architect has been tasked with designing a new environment for a company's growing needs, and has obtained this information:

* Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.

* In a true Disaster, the business can withstand a day of data loss and half a day of downtime.

* The company is one year into a 5-year contact with the co-lo data center.

* The building that is currently occupied no hanger has any floor space available, but the company has 3 empty racks of space. The co-lo can provide up to 11KVA of power per rack.

* There are current contacts with Dell to provide servers and with Cisco to provide the network components.

* The network team has standardized on an end-to-end 10Gb network.

Based on this information, what are two requirements for the new design? (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: B, C

the business can withstand a day of data loss --> this is RPO 24hrs (there is no option for RPO in answers)half a day of downtime --> this is RTO 12hrs


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel