If a project has achieved 53 points and six of eight prerequisites, for what level of certification does the project qualify?
In this question, the project has achieved 53 points and six of eight prerequisites. This means that the project has failed to meet two prerequisites, which are mandatory requirements. Therefore, the project does not qualify for any level of LEED certification, regardless of the rating system or the adaptation. The answer is A. None.
The 4 Levels of LEED Certification and How to Achieve Them
LEED credits, prerequisites and points: How are they different?
Edwin
9 months agoHorace
9 months agoMicaela
10 months agoToi
10 months agoAntonio
10 months agoLai
10 months agoVallie
11 months agoNada
11 months agoMoira
11 months agoRanee
11 months agoKing
11 months agoCiara
11 months agoGayla
11 months agoVal
2 years agoMerissa
2 years agoAja
2 years agoJodi
2 years agoMeaghan
2 years agoVincenza
2 years agoKallie
2 years agoJettie
2 years agoAnna
2 years agoVeronique
2 years agoAlaine
2 years agoMeaghan
2 years agoMalissa
2 years agoSelene
2 years agoEmily
2 years agoJacki
2 years agoRobt
2 years agoGenevive
2 years agoKelvin
2 years agoGussie
2 years agoValda
2 years ago