A project team has ended all their performance periods between August 1st and August 31st. When is the latest date that the project team can submit for preliminary review?
If a project team ends all their performance periods between August 1st and August 31st, the latest date they can submit for preliminary review is within 60 days of the end of their performance period. Therefore, the latest submission date would be October 30th, given the 60-day timeframe after the end of August. Reference: 04 GA05 Guide to LEED Certification: Commercial and GA06 LEED Fee