A project team would like to attempt the credit Transit Facilities' and is working with the local transit agency to inventory the existing and proposed bus stops within the project boundary. Oi the five proposed bus stops, one stop will be in operation at the same time when the project completes, and two stops will be in operation in the second year alter the project's completion. The remaining two bus stops will be in operation m me third year after the project's completion. How many proposed bus stops can the project team Include in the application form to attempt the credit?
A) One
B) Two
C) Three
D) Five

US Green Building Council LEED AP ND Exam - Topic 9 Question 27 Discussion

Actual exam question for US Green Building Council's LEED AP ND exam
Question #: 27
Topic #: 9
[All LEED AP ND Questions]

A project team would like to attempt the credit Transit Facilities' and is working with the local transit agency to inventory the existing and proposed bus stops within the project boundary. Oi the five proposed bus stops, one stop will be in operation at the same time when the project completes, and two stops will be in operation in the second year alter the project's completion. The remaining two bus stops will be in operation m me third year after the project's completion. How many proposed bus stops can the project team Include in the application form to attempt the credit?

Show Suggested Answer Hide Answer
Suggested Answer: A

For the Green Infrastructure and Buildings Credit on Transit Facilities, only bus stops that are operational by the time of project completion can be included in the credit documentation. In this scenario, since only one of the proposed bus stops will be in operation at the time of project completion, only this stop can be included in the application form. Stops that will become operational after project completion cannot be counted toward the credit.


LEED v4 Neighborhood Development Guide: This guide discusses the credit criteria for Transit Facilities, specifying that only currently operational or immediately operational stops can be included (USGBC, LEED v4 Neighborhood Development Current Version).

LEED Reference Guide for Neighborhood Development: Offers specific instructions on documenting transit facilities, including the requirement that stops must be operational at project completion (USGBC, LEED Reference Guide for Neighborhood Development).

Contribute your Thoughts:

0/2000 characters
Joanna
3 days ago
I feel like the answer is A) One. Makes sense.
upvoted 0 times
...
Leslie
8 days ago
So, we can only count that one stop.
upvoted 0 times
...
Felicidad
13 days ago
Yeah, only one stop is operational at completion.
upvoted 0 times
...
Alecia
18 days ago
This question is tricky. I think it's about timing.
upvoted 0 times
...
Gerardo
23 days ago
Two stops in the second year, so yeah, three seems right.
upvoted 0 times
...
Samuel
28 days ago
Wait, are they sure about the timeline? Sounds off.
upvoted 0 times
...
Danilo
1 month ago
Definitely three stops can be included!
upvoted 0 times
...
Billy
1 month ago
I think they can only count the ones operational at completion.
upvoted 0 times
...
Leslee
1 month ago
The project has five proposed bus stops.
upvoted 0 times
...
Jestine
2 months ago
I feel like we can include all five since they are all proposed, but only some will be operational at different times.
upvoted 0 times
...
Johnna
2 months ago
I'm not entirely sure. Are we supposed to include the stops that will be operational after the project is done?
upvoted 0 times
...
Octavio
2 months ago
I remember a similar question where we had to consider future operations too. Could it be three since two will be operational in the second year?
upvoted 0 times
...
Loise
2 months ago
I think we should only count the bus stops that are operational at the time of the project completion, so maybe just one?
upvoted 0 times
...
Orville
2 months ago
I'm a bit confused about the timeline. If one is operational now and two later, does that mean we can count all three?
upvoted 0 times
...
Buddy
4 months ago
This reminds me of a practice question where we had to evaluate similar criteria for bus stops. I feel like we might be able to include two stops.
upvoted 0 times
...
Izetta
4 months ago
I think we can only count the stops that are in operation at the time of application, so maybe just one?
upvoted 0 times
...
Avery
4 months ago
I remember something about counting operational bus stops, but I'm not sure if we include the ones that aren't operational yet.
upvoted 0 times
...