SNIA S10-300 Exam - Topic 7 Question 27 Discussion
An existing SAN is presently deployed that has two arrays (8FC ports each) and eight Servers (2FC ports each) two backup servers (4 FC Ports Each) and four FC to SCSI tape routers (2 port each). They presently have two Fabric each with a single 32 port switch. They wish to add four new servers, one new array, and one new backup server. Which statement is correct?
B) An additional pair of switches would be needed to enable this request
A) The existing switch infrastructure will handle the expansion
C) An additional 3 switches should be ordered to allow conversion of these fabrics to a core-edge design.
D) The added latency of the ISL would require that the backup server would need to be deployed on the same switch as the tape routers.