ServiceNow CIS-SPM Exam - Topic 4 Question 37 Discussion

Posted by Leoma on May 03, 2025 at 03:50 PM

The Project management application supports two types of external dependencies. What are they?

Choose 2 answers

Suggested Answer: A, D

The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in theProduct Documentationfor ServiceNow.


Get Premium CIS-SPM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
37 comments · newest first
BE
Becky 10 months ago
Yup, Hard and Soft are the correct ones!
HE
Herman 10 months ago
I thought it was Task Dependency instead of Soft Dependency?
LI
Lindy 11 months ago
Hard Dependency and Soft Dependency are the two types.
JA
Jacquelyne 11 months ago
Definitely Hard and Soft Dependencies!
AR
Art 11 months ago
Wait, are you sure about Soft Dependency? Sounds off.
JA
Jaclyn 11 months ago
I’m leaning towards Hard and Soft Dependencies, but I might be mixing it up with something else we studied.
AR
Arminda 11 months ago
I feel like Change Dependency sounds familiar, but I can't recall if it's actually one of the types we discussed.
JE
Jeniffer 12 months ago
I remember practicing a question about dependencies, and I think Soft Dependency was one of the options.
AN
Angelyn 12 months ago
I think one of the dependencies is definitely Hard Dependency, but I'm not sure about the second one.
MA
Marshall 1 year ago
I've got a good feeling about this. Hard Dependency and Milestone Dependency seem like the two external dependencies the application supports. Time to mark those down.
TI
Tijuana 1 year ago
Let me re-read the question and options closely. I want to make sure I understand the difference between the types of dependencies before selecting my answers.
MA
Margurite 1 year ago
Wait, I'm not sure about this. Is Task Dependency one of the options? I remember learning about that in class, but I can't recall if it's considered an external dependency.
TA
Tamra 1 year ago
Okay, I've got this. The two types of external dependencies are Hard Dependency and Soft Dependency. I'm confident those are the correct answers.
RI
Ria 1 year ago
Hmm, this looks like a tricky one. I'll need to think carefully about the different types of dependencies mentioned in the course material.
BE
Bernadine 1 year ago
I know this one! A) Hard Dependency and D) Soft Dependency are the external dependencies. The other options are just red herrings to confuse us. *laughs* Joke's on them, I'm too smart for that!
JA
Jamey 1 year ago
↳ replying to Bernadine
It's always good to double check, but I'm confident those are the correct choices.
DI
Diane 1 year ago
↳ replying to Bernadine
I had a feeling those were the right answers. Good job figuring it out!
PA
Pauline 1 year ago
↳ replying to Bernadine
Yeah, those are the two types of external dependencies supported by the Project management application.
NI
Nina 1 year ago
↳ replying to Bernadine
I think you're right! A) Hard Dependency and D) Soft Dependency are the correct ones.
FR
Francine 1 year ago
Hold up, are we sure C) Change Dependency isn't a thing? I mean, that sounds like it could be a real dependency type, right? Anyway, I'm going with A) and D).
JE
Jesus 1 year ago
↳ replying to Francine
I'm pretty sure C) Change Dependency is not a valid type. I'll go with A) and D) as well.
AM
Amos 1 year ago
↳ replying to Francine
I think C) Change Dependency is not one of the types supported. I'm going with A) and E).
MO
Monte 1 year ago
Hmm, let me think... Ah, got it! The correct answers are A) Hard Dependency and D) Soft Dependency. I can't believe they tried to trick us with all these other options.
JU
Juan 1 year ago
↳ replying to Monte
I agree, the other options seemed like distractions.
SH
Sheridan 1 year ago
↳ replying to Monte
Yeah, those were the only two options that made sense to me.
DA
Darrin 1 year ago
↳ replying to Monte
I think you're right, A) Hard Dependency and D) Soft Dependency are the correct answers.
ER
Erinn 1 year ago
I'm not sure about Change Dependency. I think it's more about internal dependencies.
AM
Amber 1 year ago
I agree with Ciara. Hard Dependency and Task Dependency make sense for project management.
HU
Hubert 1 year ago
Easy peasy! The two types of external dependencies are Hard Dependency and Soft Dependency. The others are just distractions.
AL
Alise 1 year ago
↳ replying to Hubert
It's important to understand the difference between the two types of external dependencies to effectively manage project tasks.
SA
Santos 1 year ago
↳ replying to Hubert
Yes, Task Dependency and Milestone Dependency are not the types of external dependencies supported by the Project management application.
MA
Ma 1 year ago
↳ replying to Hubert
I agree, Hard Dependency and Soft Dependency are the correct types of external dependencies.
CA
Carolann 1 year ago
I'm pretty sure the correct answers are A) Hard Dependency and D) Soft Dependency. Task Dependency and Milestone Dependency aren't external dependencies.
MA
Matthew 1 year ago
↳ replying to Carolann
Thanks for clarifying, I'll go with A) Hard Dependency and D) Soft Dependency.
LE
Lemuel 1 year ago
↳ replying to Carolann
I agree, Task Dependency and Milestone Dependency are not external dependencies.
RE
Renato 1 year ago
↳ replying to Carolann
I think you're right. Hard Dependency and Soft Dependency are the correct answers.
CI
Ciara 1 year ago
I think the two types of external dependencies are Hard Dependency and Task Dependency.