Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ServiceNow CIS-SPM Exam - Topic 1 Question 54 Discussion

When creating a planning item, which fields are populated automatically with the Approved start date value and the Approved end date value respectively?Choose 2 answers
B) Planned start date and C) Planned end date
A) Actual start date
D) Due date

ServiceNow CIS-SPM Exam - Topic 1 Question 54 Discussion

Actual exam question for ServiceNow's CIS-SPM exam
Question #: 54
Topic #: 1
[All CIS-SPM Questions]

When creating a planning item, which fields are populated automatically with the Approved start date value and the Approved end date value respectively?

Choose 2 answers

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

0/2000 characters
Augustine
49 minutes ago
Wait, isn't it A and D?
upvoted 0 times
...
Galen
5 days ago
Totally agree, B and C make sense!
upvoted 0 times
...
Truman
10 days ago
I think it's B and C.
upvoted 0 times
...
Ahmed
16 days ago
I feel like the Due date isn't related to the Approved dates at all, but I can't recall what the second answer should be.
upvoted 0 times
...
Ruthann
21 days ago
I'm a bit confused; I thought the Actual start date was linked to the Approved dates, but now I’m not so sure.
upvoted 0 times
...
Stephaine
26 days ago
I remember practicing a question like this, and I think the Planned end date is one of the fields that gets populated.
upvoted 0 times
...
Tamala
1 month ago
I think the Approved start date might automatically fill the Planned start date, but I'm not entirely sure about the end date.
upvoted 0 times
...

Save Cancel