ServiceNow Exam CIS-SPM Topic 1 Question 2 Discussion

Actual exam question for ServiceNow's Certified Implementation Specialist - Strategic Portfolio Management exam
Question #: 2
Topic #: 1
[All Certified Implementation Specialist - Strategic Portfolio Management Questions]

Using the Request type field on a resource plan, which options can be used to request a resource?

Choose 3 answers

Show Suggested Answer Hide Answer
Suggested Answer: B, C, D

Using the Request type field on a resource plan, you can request a resource by specifying the amount of FTE, person days, or hours that you need for a task or a project. FTE stands for full-time equivalent and represents the percentage of a standard work week that a resource can perform. Person days are the number of days that a resource works on a task or a project. Hours are the number of hours that a resource works on a task or a project. You can find more information about the Request type field in theProduct Documentationfor ServiceNow.