When creating a project from demand, what related records are moved and copied upon Project Creation?

Suggested Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.


Get Premium CIS-SPM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
32 comments · newest first
MA
Mattie 11 months ago
B sounds interesting, but I don’t think it’s right.
GA
Galen 11 months ago
I agree with A, that’s what I remember too.
AD
Adelina 11 months ago
Wait, are we sure about that? Seems off.
AR
Arlette 12 months ago
I thought it was C, but A makes more sense.
MI
Ming 12 months ago
Definitely A! Resource Plan and Cost Plan are key.
CI
Ciara 1 year ago
I have a vague memory of Change Requests being important, but I can't remember if they get copied. Was it B?
BO
Bok 1 year ago
I practiced a similar question, and I recall that Cost Plans are usually part of the project setup. Could it be D?
GL
Glenn 1 year ago
I'm not entirely sure, but I feel like Resource Plans are definitely involved. Maybe it's A?
BA
Barney 1 year ago
I think the correct answer might be C, since I remember that Ideas and Demands are often linked in project creation.
WI
Wilda 1 year ago
I'm feeling confident about this one. Based on my understanding, when a project is created from a demand, the idea and demand records themselves are what get copied over, not the resource plan or cost plan. The new project then has its own resource and cost plans developed.
GO
Golda 1 year ago
Ah, I've seen questions like this before. I believe the key is understanding the relationship between the demand and the project. The resource plan and cost plan are likely the main records that would be moved or copied over during project creation.
NO
Norah 1 year ago
Hmm, I'm a bit unsure about this one. I know project creation involves transferring some information from the demand, but I can't quite recall which specific records are involved. I'll have to review my notes to refresh my memory.
VA
Val 1 year ago
This seems like a straightforward question about project management. I'll need to think through the different records that are typically associated with a project and which ones would be moved or copied during project creation.
TE
Tess 1 year ago
I've used the "Current User" filter before, and I'm pretty confident that option D is the correct answer. It will only show records where the current user is listed as the Policy Owner.
SH
Shaniqua 1 year ago
Alright, I've got this. The system can establish multiple redundant uplinks, and it prevents cloud consumers from losing connectivity. That's options A and B. As for the other two, I'm pretty confident they're not true.
PR
Providencia 1 year ago
The way they want to check function calls and decision points sounds a lot like what we practiced in our last mock review.
LE
Leota 1 year ago
Wait, there's no option for 'all of the above'? This exam is clearly rigged!
SU
Sue 1 year ago
A) Resource Plan and Cost Plan? Hmm, sounds a bit too simplistic. I'm going to have to go with the more comprehensive C) Idea and Demand.
IZ
Izetta 1 year ago
↳ replying to Sue
C) Idea and Demand? That seems like the most comprehensive option. I agree with that choice.
MI
Mitsue 1 year ago
↳ replying to Sue
B) Resource Plan and Change Requests? I don't think that covers everything. I'm leaning towards C) Idea and Demand.
CO
Colette 1 year ago
↳ replying to Sue
A) Resource Plan and Cost Plan? That does sound a bit basic. I think C) Idea and Demand makes more sense.
LU
Luis 1 year ago
D) Cost Plan and Assessment? Really? That's a bit of a stretch, don't you think? I'm going with C, it just makes the most sense.
GL
Glenn 1 year ago
↳ replying to Luis
Yeah, Resource Plan and Change Requests seem important too, but I still think Idea and Demand are the most relevant.
EL
Elly 1 year ago
↳ replying to Luis
I agree, it wouldn't make sense for Cost Plan and Assessment to be moved and copied upon Project Creation.
CA
Cathrine 1 year ago
↳ replying to Luis
I think C is the right answer, Idea and Demand are definitely related records that should be moved and copied.
MA
Matilda 2 years ago
B) Resource Plan and Change Requests seems like the right answer to me. Gotta have those resources and change requests ready to go!
DE
Devora 1 year ago
↳ replying to Matilda
Yes, those are definitely important records to have when creating a project from demand.
FE
Fernanda 1 year ago
↳ replying to Matilda
I agree, having the resource plan and change requests is crucial for a project.
DA
Dan 2 years ago
I think the correct answer is C) Idea and Demand. That's the logical choice when creating a project from demand.
SH
Shannon 2 years ago
I'm not sure, but I think it could also be Resource Plan and Change Requests.
MY
Myong 2 years ago
I agree with Janessa, Resource Plan and Cost Plan make sense to be moved and copied.
JA
Janessa 2 years ago
I think the related records moved and copied are Resource Plan and Cost Plan.