Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Scrum PSD Exam - Topic 3 Question 88 Discussion

Actual exam question for Scrum's PSD exam
Question #: 88
Topic #: 3
[All PSD Questions]

When using Scrum, can a Scrum Team use Continuous Delivery? (choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: E

Scrum is compatible with Continuous Delivery as long as each Increment meets the Definition of Done. Continuous Delivery aligns with Agile principles, allowing frequent releases.


Contribute your Thoughts:

0/2000 characters
Goldie
18 days ago
I agree, E is the best answer!
upvoted 0 times
...
Gianna
23 days ago
Continuous Delivery can totally work with Scrum!
upvoted 0 times
...
Alaine
1 month ago
I remember our instructor saying that the Product Owner's role is key in deciding releases, so maybe that rules out Continuous Delivery in some cases?
upvoted 0 times
...
Jennifer
1 month ago
I feel like option E makes sense because Scrum is flexible, but I’m not entirely confident about how it aligns with Continuous Delivery.
upvoted 0 times
...
Annelle
2 months ago
I think we practiced a question similar to this, and I recall that the Definition of Done is crucial before any release.
upvoted 0 times
...
Leonida
2 months ago
I remember discussing how Scrum emphasizes the importance of the Sprint Review, but I'm not sure if that completely rules out Continuous Delivery.
upvoted 0 times
...

Save Cancel