Scrum PSD Exam - Topic 3 Question 88 Discussion

Actual exam question for Scrum's PSD exam
Question #: 88
Topic #: 3
[All PSD Questions]

When using Scrum, can a Scrum Team use Continuous Delivery? (choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: E

Scrum is compatible with Continuous Delivery as long as each Increment meets the Definition of Done. Continuous Delivery aligns with Agile principles, allowing frequent releases.