Posted by Daniel on Apr 05, 2026 at 08:15 PM

Who is responsible for a sprint backlog item that contains several database tasks?

Suggested Answer: A

Developers are responsible for conducting the work on the sprint backlog


Get Premium PSD Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
HA
Harrison 3 months ago
But the developers are responsible for the sprint backlog overall, right? So A makes sense.
PH
Phillip 3 months ago
I disagree, it could be C) The company's database specialist. They have the expertise.
TR
Tresa 3 months ago
I think it's A) The developers. They should handle the tasks.
TR
Trina 3 months ago
Really? I thought the product owner had more control over the backlog.
MI
Miriam 3 months ago
I disagree, the Scrum master just facilitates, not responsible for tasks.
SU
Suzi 4 months ago
Wait, isn't the database specialist responsible for those tasks?
EV
Evette 5 months ago
I think the product owner should be involved too.
ME
Merilyn 5 months ago
Definitely the developers! They handle the tasks.
RO
Rosalind 6 months ago
I thought the Scrum master was there to facilitate, not to take responsibility for specific tasks, but I could be wrong.
HE
Helene 6 months ago
I feel like the database specialist might have a role, but I don't recall if they're officially responsible for the backlog items.
EL
Elliott 6 months ago
I remember a practice question where the product owner was mentioned, but I don't think they handle the tasks directly.
SH
Shawna 6 months ago
I think the developers are responsible for the sprint backlog items, but I'm not completely sure if that includes database tasks specifically.