Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Scrum Exam PSD Topic 1 Question 38 Discussion

Actual exam question for Scrum's PSD exam
Question #: 38
Topic #: 1
[All PSD Questions]

What happens if the Scrum Team cannot complete its work by the end of the Sprint? (choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: D

There is no time in between sprints, so there cannot be activities.


Contribute your Thoughts:

Gwen
10 days ago
I agree, B) is the correct answer. Extending the sprint length is not the right approach, as Scrum emphasizes continuous improvement.
upvoted 0 times
...
Markus
12 days ago
I see both points, but I think C could also work. Extending the Sprint and using the new duration for future Sprints can help improve the team's efficiency.
upvoted 0 times
...
Dahlia
16 days ago
I disagree, I believe B is the best option. The team should stick to the Sprint length and focus on continuous learning and adaptation.
upvoted 0 times
...
Dona
17 days ago
B) seems like the best option. The Scrum team should learn and adapt for future sprints, rather than just extending the current one.
upvoted 0 times
...
Ivan
17 days ago
I think the best answer is A. Extending the Sprint temporarily can help the team learn from their mistakes.
upvoted 0 times
...

Save Cancel