Several scrum teams share the scrum master. Developers of multiple teams approach the scrum master, because they need fulltime commitment from the same technical specialist for the next sprint. What should the scrum master consider for the response to this problem? Choose the two best answers.
The working increment is the goal of the sprint and should be kept in mind. The self-managing aspect of the teams is also crucial to take in mind. Stable velocity and optimally used developers are not the scrum master's concern.