Which option should be the next Agile Release Train (ART) to launch to leverage the full flow of value?
Suggested Answer: C
Get Premium SAFe-SPC Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
To maximize the flow of value, SAFe recommends launching the next ART in the same value stream. This approach builds synergy, enables better integration, and accelerates end-to-end value delivery by reducing cross-ART dependencies and optimizing flow within the value stream.
SAFe 6.0, ''Designing the Implementation'' (Selecting Next ARTs)
SPC 6.0 Guide, ''Designing the Implementation''
5 comments · newest first
QU
Quentin
2 days ago
I think option C makes the most sense.
AM
Ammie
7 days ago
I feel like the next train to volunteer might not always be the best choice, especially if it doesn't align with our current goals.
JO
Joanna
13 days ago
I'm a bit confused about the difference between value streams and portfolios. Wouldn't launching a train in a different value stream still be beneficial?
AA
Aaron
18 days ago
I remember a practice question where we had to choose between different trains, and I think the one that aligns with the current value stream was the best option.
QU
Queen
23 days ago
I think we discussed that launching a train in the same value stream could help maximize value flow, but I'm not entirely sure.