What does assigning business value to a team's Pl Objectives influence?
C) How teams plan the implementation
A) How the Kanban work in process limits are set
B) How to achieve objectives

Scaled Agile SAFe-RTE Exam - Topic 2 Question 67 Discussion

Actual exam question for Scaled Agile's SAFe-RTE exam
Question #: 67
Topic #: 2
[All SAFe-RTE Questions]

What does assigning business value to a team's Pl Objectives influence?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

0/2000 characters
Demetra
25 days ago
I think it also influences achieving objectives.
upvoted 0 times
...
Ashanti
30 days ago
It definitely affects how teams plan the implementation.
upvoted 0 times
...
Jennifer
1 month ago
I practiced a similar question, and I think it was about prioritizing tasks based on business value. So, I lean towards option A being correct.
upvoted 0 times
...
Edison
2 months ago
I feel like it might relate to how to achieve objectives too. Maybe it's a mix of A and C? I need to double-check my notes.
upvoted 0 times
...
Elena
2 months ago
I'm not entirely sure, but I remember something about work in process limits being affected by business value. Could it be option B?
upvoted 0 times
...
Gerry
2 months ago
I think assigning business value to the team's objectives mainly influences how they plan the implementation, right? It helps prioritize tasks.
upvoted 0 times
...

Save Cancel