Scaled Agile SAFe-RTE Exam - Topic 1 Question 35 Discussion
When planning for a distributed Program Increment (PI) Planning event with a large dif-ference in time zones, what are two key preparation and facilitation focus areas for a Re-lease Train Engineer (RTE)? (Choose two.)
C) Adjust the PI agenda to 2.5 -- 3 days, allowing for overlapping hours
A) Share the outcomes of preparation meetings with local Scrum Masters so they can arrange local rooms
B) Have a single RTE and technical support person that acts as a central point of communication for all locations
D) Split up the PI Planning event per time zone and then have the final plan review, confidence vote, and planning retrospective as one centralized meeting
E) Arrange and test presentation audio and video connectivity in all locations
Vanna
9 months agoLeslie
9 months agoVallie
10 months agoMicah
10 months agoRoy
10 months agoThea
10 months agoSharita
10 months agoDahlia
11 months agoDelfina
11 months agoJina
11 months agoJeannetta
11 months agoWinifred
11 months agoVannessa
11 months agoMireya
11 months agoSantos
11 months agoLyda
1 year agoSylvia
1 year agoGertude
1 year agoJulio
1 year agoDudley
1 year agoKarina
1 year agoVeta
1 year agoDaron
1 year agoKaitlyn
1 year agoNguyet
1 year agoFrancene
1 year agoElizabeth
1 year agoAlisha
1 year agoBillye
1 year ago