Scaled Agile Exam SAFe-RTE Topic 1 Question 21 Discussion

Actual exam question for Scaled Agile's SAFe-RTE exam
Question #: 21
Topic #: 1
[All SAFe-RTE Questions]

At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Yuriko
1 days ago
I agree with Virgina, that's what the answer option B says. It makes sense to review those aspects at the end of day two.
upvoted 0 times
...
Virgina
5 days ago
I think the final plan review covers changes to capacity and load, final PI objectives, program risks and impediments.
upvoted 0 times
...
Art
10 days ago
I believe the final plan review also includes planned Features, uncommitted objectives, and ROAMed risks.
upvoted 0 times
...
Dell
11 days ago
I agree with Shawnta. It's important to review all those aspects at the end of day two of the PI Planning event.
upvoted 0 times
...
Shawnta
15 days ago
I think the final plan review covers changes to capacity and load, final PI objectives, program risks and impediments.
upvoted 0 times
...