Scaled Agile SAFe-RTE Exam - Topic 1 Question 21 Discussion
At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?
D) Planned Features, uncommitted objectives, and ROAMed risks
A) Team Features, Stories, and team-level enablers
B) Changes to capacity and load, final PI objectives, program risks and impediments
C) Changes to iteration goals, measured velocity, and dependencies
Theron
6 months agoArlen
6 months agoJosephine
7 months agoAlaine
7 months agoValene
7 months agoMicaela
7 months agoSol
7 months agoAdelina
8 months agoSonia
8 months agoLavera
8 months agoRolland
8 months agoRosalind
8 months agoNoah
8 months agoSommer
8 months agoEdgar
8 months agoMaryln
8 months agoGeorgiann
8 months agoIra
8 months agoNguyet
1 year agoBo
1 year agoCarri
1 year agoSheron
12 months agoKris
12 months agoVicki
1 year agoTennie
1 year agoArlean
12 months agoHolley
12 months agoKenneth
1 year agoSharika
1 year agoKimberlie
1 year agoLoreta
1 year agoLeslie
1 year agoMelita
1 year agoYuriko
1 year agoVirgina
1 year agoArt
1 year agoDell
1 year agoShawnta
1 year ago