Scaled Agile Exam SAFe-Agilist Topic 8 Question 30 Discussion

Actual exam question for Scaled Agile's SAFe-Agilist exam
Question #: 30
Topic #: 8
[All SAFe-Agilist Questions]

The program board shows which two items? (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Joanna
3 months ago
Capacity and load, that's a no-brainer. As for the other one, I'm thinking significant dependencies. Wait, does the program board also show the weather forecast? You never know with these certification exams.
upvoted 0 times
...
Reta
3 months ago
Risks? Features? Epics? What is this, a test for mind readers? I'm just going to go with capacity and load, and see if I can guess the other one.
upvoted 0 times
...
Sabra
3 months ago
This seems straightforward - the program board definitely shows capacity and load, and I think it also shows significant dependencies. Hopefully, I've got this one figured out.
upvoted 0 times
Jaime
2 months ago
B) Capacity and load
upvoted 0 times
...
Layla
2 months ago
A) Risks
upvoted 0 times
...
...
Tula
3 months ago
Hmm, I'm pretty sure the program board shows capacity and load, but I'm not sure about the other one. Guess I'll have to think hard on this one.
upvoted 0 times
Angelyn
2 months ago
B) Capacity and load
upvoted 0 times
...
Noah
2 months ago
A) Risks
upvoted 0 times
...
...
Ling
4 months ago
I believe Capacity and load should also be shown on the program board to ensure resources are managed effectively.
upvoted 0 times
...
Ramonita
4 months ago
I agree with Amie. Risks and Significant dependencies are crucial for tracking progress.
upvoted 0 times
...
Amie
4 months ago
I think the program board shows Risks and Significant dependencies.