Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP C_TPLM22_67 Exam

Status: RETIRED
Exam Name: SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Exam Code: C_TPLM22_67
Related Certification(s): SAP Project System with SAP ERP 6.0 EHP4 Certification
Certification Provider: SAP
Actual Exam Duration: 180 Minutes
Number of C_TPLM22_67 practice questions in our database: 165 (updated: 02-01-2023)
Expected C_TPLM22_67 Exam Topics, as suggested by SAP :
  • Topic 1: Configure cost center reporting and create report painter reports/ Describe the characteristics of Revenues & Payments
  • Topic 2: Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement
  • Topic 3: Determine general reporting requirements and reporting requirements for cost centers/ Describe how the Resource Planning process integrates with HCM
  • Topic 4: Name the components of Work Breakdown Structure, Network and activities, Milestones/ Revenues and Payments
  • Topic 5: Describe procedures for establishing budgets and reporting costs/ Project Structures
Disscuss SAP C_TPLM22_67 Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!

Free SAP C_TPLM22_67 Exam Actual Questions

Note: Premium Questions for C_TPLM22_67 were last updated On 02-01-2023 (see below)

Question #1

Which of the following types of reports are avaialable for financial reporting? (2)

Reveal Solution Hide Solution
Correct Answer: B, D

Question #2

Which type of reports allows you to choose the objects whose costs you want to analyze or call up an appropriate list and choose the period you want to evaluate?

Please choose the correct answer.

Response:

Reveal Solution Hide Solution
Correct Answer: B

Question #3

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?

Please choose the correct answer.

Response:

Capacity planning board

Reveal Solution Hide Solution
Correct Answer: B

Question #4

Which of the following can be used to calculate and update interest in SAP project system?

There are 2 correct answers to this question.

Response:

Reveal Solution Hide Solution
Correct Answer: A, B

Question #5

Which parameters determine if the network header or network activities are cost objects?

There are 2 correct answers to this question.

Response:

Reveal Solution Hide Solution
Correct Answer: A, B


Unlock Premium C_TPLM22_67 Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel