Question #: 39
Topic #: 4
[All E_S4HCON2023 Questions]

You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for the last time?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Misty
3 days ago
I'm going with A. The cleanup process just seems like the logical time to stop the shadow instance and get everything ready for the big day.
upvoted 0 times
...
Lakeesha
4 days ago
B is the correct answer, isn't it? I mean, we need to stop the shadow instance before the downtime starts so we can move forward with the cutover, right?
upvoted 0 times
...
Julieta
4 days ago
C seems like the obvious choice to me. Why would we stop the shadow instance early in the downtime? That just doesn't make sense.
upvoted 0 times
...
Lavonda
25 days ago
I agree with Gerald, stopping it early makes sense to ensure a smooth conversion process.
upvoted 0 times
...
Gerald
1 months ago
I believe it will be stopped early in the downtime to avoid any issues.
upvoted 0 times
...
Alpha
1 months ago
I'm pretty sure it's option D. After all, we want to keep the shadow instance running as long as possible to ensure a smooth transition, right?
upvoted 0 times
Edmond
22 days ago
I agree with you. It's important to have a clear timeline for when the shadow instance will be stopped.
upvoted 0 times
...
Jesusita
28 days ago
I think it's option B. We need to stop the shadow instance before the downtime starts to avoid any issues.
upvoted 0 times
...
...
Barb
1 months ago
I think the shadow instance will be stopped at the end.
upvoted 0 times
...