SAP E_ACTAI_2403 Exam - Topic 3 Question 17 Discussion

Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 17
Topic #: 3
[All E_ACTAI_2403 Questions]

When does the product owner accept or reject the user stories included in the Sprint?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Tijuana
3 months ago
User acceptance test seems too late for that.
upvoted 0 times
...
Isreal
3 months ago
Wait, is it really not during the daily Scrum?
upvoted 0 times
...
Lauran
3 months ago
100% agree, it's the Sprint Review!
upvoted 0 times
...
Nu
4 months ago
I thought it was during the Quality Gate?
upvoted 0 times
...
Marnie
4 months ago
Definitely during the Sprint Review!
upvoted 0 times
...
Shawana
4 months ago
I don’t think it’s during the daily Scrum meeting, but I can't recall the exact reason why.
upvoted 0 times
...
Nu
4 months ago
I’m a bit confused; I thought it could be during the user acceptance test, but that might be for a different phase.
upvoted 0 times
...
Serita
4 months ago
I remember a practice question about this, and I think it was also about the Sprint Review. That seems right to me.
upvoted 0 times
...
Noe
5 months ago
I think the product owner accepts or rejects user stories during the Sprint Review, but I'm not entirely sure.
upvoted 0 times
...
Tonja
5 months ago
The Sprint Review seems like the most logical time for the product owner to review and accept or reject the user stories, since that's when the team presents the work they've completed. I'll go with option A.
upvoted 0 times
...
Darrin
5 months ago
Hmm, I'm a bit confused about this one. I know the product owner is involved in the process, but I'm not sure exactly when they make the call on the user stories. I'll have to think this through carefully.
upvoted 0 times
...
Bambi
5 months ago
I'm pretty sure the product owner accepts or rejects user stories during the Sprint Review, so I'll go with option A.
upvoted 0 times
...
Ashanti
5 months ago
I'm leaning towards option B, the Quality Gate, since that's when the team checks if the user stories meet the acceptance criteria. But I could be misremembering the details, so I'll double-check my notes before answering.
upvoted 0 times
...
Kerry
5 months ago
I feel like $14,900 sounds close, but I can't really remember if we add or subtract certain expenses like utilities or materials.
upvoted 0 times
...
Agustin
1 year ago
Ah, the age-old question of when the product owner takes a look at the user stories. I'm going to have to go with A) During the Sprint Review. Anything else would be like trying to herd cats - good luck with that!
upvoted 0 times
...
Cherelle
1 year ago
I'm going with A) During the Sprint Review. It's the moment of truth where the product owner can make their stamp of approval (or disapproval) on the work. Anything else would just be strange.
upvoted 0 times
Casie
1 year ago
Definitely, it's important for the product owner to review and accept the work during the Sprint Review.
upvoted 0 times
...
Elenore
1 year ago
Yes, that's when the product owner can see the actual work done and provide feedback.
upvoted 0 times
...
Theola
1 year ago
I agree, the Sprint Review is the right time for the product owner to accept or reject user stories.
upvoted 0 times
...
...
Adrianna
1 year ago
D) During the user acceptance test
upvoted 0 times
...
Janessa
1 year ago
I disagree, I believe it should be during the Sprint Review because that's when stakeholders are present to provide feedback.
upvoted 0 times
...
Herman
1 year ago
B) During the Quality Gate
upvoted 0 times
...
Lelia
1 year ago
I think it makes sense for the product owner to accept or reject user stories during the Sprint Review.
upvoted 0 times
...
Mollie
1 year ago
D) During the user acceptance test? Really? That's like trying to return a pizza after you've already eaten it. The product owner should be involved much earlier in the process.
upvoted 0 times
Leah
1 year ago
B) During the Quality Gate
upvoted 0 times
...
Leah
1 year ago
Yes, the Sprint Review is where the product owner accepts or rejects the user stories.
upvoted 0 times
...
Leah
1 year ago
A) During the Sprint Review
upvoted 0 times
...
...
Janessa
1 year ago
A) During the Sprint Review
upvoted 0 times
...
Kent
1 year ago
I think the correct answer is A) During the Sprint Review. The Sprint Review is the perfect opportunity for the product owner to review the work and provide their acceptance or rejection.
upvoted 0 times
Carmela
1 year ago
During the Sprint Review, the product owner can provide feedback and make decisions on the user stories.
upvoted 0 times
...
Carin
1 year ago
Yes, the Sprint Review is where the product owner ensures that the user stories meet the acceptance criteria.
upvoted 0 times
...
Daniel
1 year ago
That's correct, it's important for the product owner to review the work during that time.
upvoted 0 times
...
Hubert
1 year ago
I agree, the product owner accepts or rejects user stories during the Sprint Review.
upvoted 0 times
...
...
Francesco
1 year ago
The product owner accepts or rejects the user stories during the Sprint Review. That's when they can provide feedback and ensure the team delivered the expected functionality.
upvoted 0 times
Bethanie
1 year ago
The user acceptance test is where the product owner can formally accept or reject the user stories.
upvoted 0 times
...
Joseph
1 year ago
D) During the user acceptance test
upvoted 0 times
...
Alaine
1 year ago
The product owner reviews the user stories during the Sprint Review to provide feedback.
upvoted 0 times
...
Marta
1 year ago
A) During the Sprint Review
upvoted 0 times
...
Marsha
1 year ago
D) During the user acceptance test
upvoted 0 times
...
Nida
1 year ago
The product owner reviews the user stories during the Sprint Review to provide feedback.
upvoted 0 times
...
Erick
1 year ago
A) During the Sprint Review
upvoted 0 times
...
...