Hmm, I'm not so sure about C. Requirement lead time seems more like a lead time for the actual demand, not the replenishment process. But the other three are definitely correct.
A, B, and D look like the right answers to me. The replenishment lead time should include the time it takes to process the purchase, the planned delivery time, and the time to process the goods receipt.