You want to set up integrated planning for your internal orders.

Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

To activate integrated planning for internal orders in SAP S/4HANA, you need to set indicators in both the CO version and the internal order master record. This setup allows for the integration of budget and actuals for better planning and tracking within Management Accounting.


Contribute your Thoughts:

0/2000 characters
Elouise
2 months ago
D is also a valid option, right?
upvoted 0 times
...
Beckie
3 months ago
Wait, can you really set it in the CO version?
upvoted 0 times
...
Pearlie
3 months ago
Definitely agree with A!
upvoted 0 times
...
Youlanda
3 months ago
Not so sure about C, seems off.
upvoted 0 times
...
Colby
3 months ago
I think A and C are the right answers.
upvoted 0 times
...
Louvenia
3 months ago
I definitely think we should set the indicator in the controlling area, but I’m torn between that and the planning profile.
upvoted 0 times
...
Zita
4 months ago
I practiced a similar question, and I feel like the internal order master record might be relevant too, but I’m not completely confident.
upvoted 0 times
...
Keena
4 months ago
I remember something about the CO version being important for integrated planning, but I can't recall if it's one of the correct answers.
upvoted 0 times
...
Jamal
4 months ago
I think we need to set the relevant indicator in the planning profile of the order type, but I'm not sure about the controlling area part.
upvoted 0 times
...
Kenneth
4 months ago
I've got this! The answer is to set the relevant indicator in the planning profile of the order type. That's where you configure the integrated planning settings for internal orders.
upvoted 0 times
...
Leah
4 months ago
Okay, let's see. I'm guessing the answer has something to do with either the controlling area, CO version, planning profile, or internal order master record. I'll need to review my notes on integrated planning to figure this out.
upvoted 0 times
...
Lonny
5 months ago
Hmm, this is a tricky one. I'm not entirely sure where the relevant indicator would be set. I'll need to think through the different options carefully.
upvoted 0 times
...
Stefan
5 months ago
I'm pretty confident I know how to approach this. I think the key is to look at the options and determine which ones are relevant to setting up integrated planning for internal orders.
upvoted 0 times
...
Brittni
5 months ago
Hmm, I'm leaning towards A and C. The controlling area and planning profile seem like the logical places to set that indicator.
upvoted 0 times
...
Emmanuel
5 months ago
I think the answer is A and D.
upvoted 0 times
...
Phillip
7 months ago
I'm pretty sure it's B and D. The CO version and the order master record are where I'd look for that setting.
upvoted 0 times
...
Lilli
7 months ago
I think it's either C or D. Gotta be in the order type or order master record, right?
upvoted 0 times
Dorcas
5 months ago
A) Set the relevant indicator in the controlling area.
upvoted 0 times
...
...

Save Cancel