You want to set up integrated planning for your internal orders.
Note: There are 2 correct answers to this question.
To activate integrated planning for internal orders in SAP S/4HANA, you need to set indicators in both the CO version and the internal order master record. This setup allows for the integration of budget and actuals for better planning and tracking within Management Accounting.