SAP C_TS470_2412 Exam - Topic 1 Question 28 Discussion

Posted by Valentin on Oct 17, 2026 at 10:53 PM

Which assignment is required in a cross-plant planning scenario?

Suggested Answer: B

In a cross-plant planning scenario, maintenance activities span multiple plants. The correct answer is B. Let's unpack this.

Cross-Plant Planning Context:

One planning plant oversees maintenance for multiple maintenance plants (where technical objects reside).

Why Several Maintenance Plants to a Planning Plant?

The planning plant is the central hub for scheduling and resource allocation. Maintenance plants (e.g., Plant 0001, Plant 0002) are assigned to it (e.g., Plant 1000) in customizing (SPRO Enterprise Structure Assignment Plant Maintenance). This ensures a single point of control for work orders and plans across plants.

Why Not the Others?

A: Planner groups are assigned within a plant, not across plants directly.

C: Multiple planning plants for one maintenance plant is illogical.

D: Planner groups operate within a planning plant, not across multiple.

Example:

Planning Plant 1000 manages maintenance for Plants 0001 and 0002.

'In cross-plant planning, several maintenance plants are assigned to a planning plant to centralize maintenance scheduling.'


Get Premium C_TS470_2412 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
0 comments · newest first

Currently there are no comments in this discussion, be the first to comment!

0/2000 characters

Save Cancel