You want to configure the organizational units for Service with Advanced Execution. Which of the following business objects can you assign to a planning plant?
In Service with Advanced Execution, organizational units are configured to support complex service scenarios. The correct answers are maintenance work center (A) and maintenance planner group (D). Let's dive deep.
Planning Plant Role:
The planning plant is the central organizational unit for maintenance and service planning, assigned in enterprise structure (SPRO Enterprise Structure).
Maintenance work center (A): A work center (e.g., 'Field Service Team') is assigned to a planning plant in its master data (IR01/IR02). It defines where work is executed and is critical for scheduling in advanced execution.
Maintenance planner group (D): A planner group (e.g., 'PLG1') is assigned to a planning plant (via IP01 or customizing) to manage planning activities (e.g., who schedules orders).
Why Not the Others?
Company code (B): A company code is a financial entity assigned to plants, not a service-specific object.
Location (C): Locations are geographic data, not directly assigned to planning plants in this context.
Advanced Execution Context:
In advanced execution, these assignments enable resource-related billing and detailed scheduling.
'In Service with Advanced Execution, maintenance work centers and planner groups are assigned to a planning plant for organizational setup.'
Currently there are no comments in this discussion, be the first to comment!