SAP C_TS452_2410 Exam - Topic 4 Question 2 Discussion
Which of the following tasks does the system perform during reorder point planning? Note: Thereare 2 correct answers to this question.
B) Carry out a lot-size calculation for every material with net requirements and C) Carry out a net requirement calculation for every material included in the planning run
A) Flag materials that have been subject to an activity relevant to MRP
D) Perform backward scheduling to determine the availability dates of purchase requisitions
Dyan
10 months agoEdelmira
10 months agoEura
10 months agoJessenia
11 months agoRikki
11 months agoLucina
11 months agoMelina
11 months agoJulie
11 months agoAntonette
11 months agoAlise
11 months agoAnnmarie
11 months agoPamela
11 months agoJuan
12 months agoRamonita
2 years agoBuck
2 years agoTomas
2 years agoAlecia
2 years agoCandra
2 years agoRose
2 years agoCarol
2 years agoJacqueline
2 years agoXochitl
2 years agoAhmed
2 years agoMitsue
2 years agoDanilo
2 years agoHoward
2 years agoCeola
2 years agoEdwin
2 years agoLeonor
2 years ago