SAP C_TS452_2410 Exam - Topic 2 Question 3 Discussion

Actual exam question for SAP's C_TS452_2410 exam
Question #: 3
Topic #: 2
[All C_TS452_2410 Questions]

Which of the following procurement proposals can be created during an MRP Live planning run for

externally procured materials? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, D

Contribute your Thoughts:

0/2000 characters
Tiffiny
3 months ago
I thought delivery schedule lines were a thing too?
upvoted 0 times
...
Alexis
3 months ago
A and B are correct, no doubt about it!
upvoted 0 times
...
Shala
3 months ago
Wait, can you really get a planned order for external materials?
upvoted 0 times
...
Phung
4 months ago
Definitely A and D!
upvoted 0 times
...
Florinda
4 months ago
I think it's A and B.
upvoted 0 times
...
Richelle
4 months ago
I feel like purchase orders might be created too, but I’m a bit confused about the differences between them and requisitions.
upvoted 0 times
...
Reuben
4 months ago
Delivery schedule lines sound familiar, but I can't recall if they are part of MRP Live planning.
upvoted 0 times
...
Jerrod
4 months ago
I remember practicing a similar question, and I think purchase requisitions are definitely one of the correct answers.
upvoted 0 times
...
Tomas
5 months ago
I think planned orders can be created during MRP Live, but I'm not sure about the other options.
upvoted 0 times
...
Emmett
5 months ago
I think the key is understanding the distinction between the different procurement proposals. Planned orders and purchase orders make sense, but I'm not sure about the others.
upvoted 0 times
...
Merlyn
5 months ago
I'm a bit confused - is a delivery schedule line also a valid option here? I'll need to double-check that.
upvoted 0 times
...
Delisa
5 months ago
Okay, I remember from the lectures that planned orders and purchase orders are both valid options for externally procured materials. I'll select those.
upvoted 0 times
...
Dorothy
5 months ago
Hmm, I'm a bit unsure about the difference between planned orders and purchase orders. I'll need to think this through carefully.
upvoted 0 times
...
Chi
5 months ago
This question seems straightforward, I'm pretty confident I can identify the two correct answers.
upvoted 0 times
...
Shawna
1 year ago
Hold on, hold on. Didn't they say there are 2 correct answers? I'm going with A) Planned order and D) Purchase requisition. Gotta read the question carefully, folks.
upvoted 0 times
Shaun
1 year ago
Yes, you're correct. Those are the two procurement proposals that can be created during an MRP Live planning run for externally procured materials.
upvoted 0 times
...
Vilma
1 year ago
I think you're right, A) Planned order and D) Purchase requisition are the correct answers.
upvoted 0 times
...
...
Shenika
1 year ago
I'm not sure about Purchase requisition. I think it's not created during an MRP Live planning run.
upvoted 0 times
...
Cherelle
1 year ago
Haha, this is easy! A) Planned order and B) Purchase order, of course. I'm the MRP master, baby!
upvoted 0 times
Harrison
1 year ago
That's correct! You really know your stuff.
upvoted 0 times
...
Harrison
1 year ago
A) Planned order and B) Purchase order
upvoted 0 times
...
...
Stephen
1 year ago
I agree with Lashandra. Planned order and Purchase order make sense for externally procured materials.
upvoted 0 times
...
Lennie
1 year ago
Definitely A) Planned order, that's a no-brainer. But I'm not sure about the other one. Maybe C) Delivery schedule line?
upvoted 0 times
Frank
1 year ago
B) Purchase order is not one of the correct answers.
upvoted 0 times
...
Cassie
1 year ago
C) Delivery schedule line could be the other correct answer.
upvoted 0 times
...
Craig
1 year ago
A) Planned order is definitely one of the correct answers.
upvoted 0 times
...
...
Lashandra
1 year ago
I think the correct answers are A) Planned order and B) Purchase order.
upvoted 0 times
...
Pearlene
1 year ago
I think both A) Planned order and D) Purchase requisition are the correct answers. MRP Live should generate planned orders and purchase requisitions for externally procured materials.
upvoted 0 times
Carla
1 year ago
It's important to have both planned orders and purchase requisitions created for externally procured materials in the planning process.
upvoted 0 times
...
Charisse
1 year ago
I think you're right, those are the two correct options for procurement proposals during an MRP Live planning run.
upvoted 0 times
...
Tish
1 year ago
MRP Live should definitely generate planned orders and purchase requisitions for externally procured materials.
upvoted 0 times
...
Alishia
1 year ago
I agree, A) Planned order and D) Purchase requisition are the correct answers.