SAP Exam C_TS422_2023 Topic 9 Question 28 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 28
Topic #: 9
[All C_TS422_2023 Questions]

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, D