What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
I'm going with B and C. Seems like the most logical explanation for the problem. Although, I do wonder if the test writers have a sense of humor... 'Finite Scheduling' - really?
Haha, I bet the person who wrote this question was just having a laugh. 'Finite Scheduling' and 'Change Planning Direction' - sounds like they're trying to trip us up!
I think the correct answers are B and C. The work center having multiple individual capacities and the alternative work centers being fully occupied can both lead to multiple commitments on the same scheduled dates.
Catarina
7 months agoRaina
7 months agoAretha
6 months agoQuentin
6 months agoJuan
7 months agoLavonne
7 months agoAlex
7 months agoShanda
7 months agoCandra
7 months agoRoy
7 months agoLavelle
8 months agoJody
8 months agoPhyliss
7 months agoTemeka
7 months agoLouvenia
8 months agoAlaine
8 months agoAlva
8 months agoBroderick
8 months ago