SAP Exam C_TS422_2022 Topic 7 Question 33 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 33
Topic #: 7
[All C_TS422_2022 Questions]

What will happen in the MRP run if you have created a new MRP-relevant material that

supports both in-house production and external procurement?

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Jerlene
20 days ago
Haha, looks like we've got a real brain-teaser here! I'm leaning towards B, but I'm half-expecting the answer to be something totally unexpected, like 'the MRP run summons a genie to decide'.
upvoted 0 times
Annalee
2 days ago
A) The MRP run assumes external procurement.
upvoted 0 times
...
...
Selma
23 days ago
I'm going to have to go with D. The MRP run can only plan the material if a quotation has been maintained, right?
upvoted 0 times
Aron
2 days ago
Yes, you are correct. The MRP run plans the material only if a quotation has been maintained.
upvoted 0 times
...
...
Lucina
1 months ago
Hmm, I'm not so sure. I think C might be the correct answer - the MRP run won't consider the new material unless it's planned interactively.
upvoted 0 times
Julian
7 days ago
But what if a quotation has been maintained for the new material? Would the MRP run plan it then?
upvoted 0 times
...
Dalene
13 days ago
I think C is correct. The MRP run won't consider the material unless it's planned interactively.
upvoted 0 times
...
...
King
2 months ago
I'm pretty sure the answer is B. The MRP run should assume in-house production for the new material since that's one of the options supported.
upvoted 0 times
Melina
24 days ago
No, I believe it's B. The MRP run should assume in-house production for the new material.
upvoted 0 times
...
Rosita
25 days ago
I think the answer is A. The MRP run should assume external procurement for the new material.
upvoted 0 times
...
...
Asha
2 months ago
But what if the material has to be planned interactively?
upvoted 0 times
...
Lyla
2 months ago
I disagree, I believe the MRP run will assume in-house production.
upvoted 0 times
...
Asha
2 months ago
I think the MRP run will assume external procurement.
upvoted 0 times
...