SAP Exam C_TS422_2022 Topic 7 Question 15 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 15
Topic #: 7
[All C_TS422_2022 Questions]

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Isreal
2 days ago
I'm pretty sure the setup time and total replenishment lead time are the correct answers here. The other options sound a bit sketchy to me.
upvoted 0 times
...
Marshall
6 days ago
Hmm, I'd say the total replenishment lead time is definitely important. But I'm not sure about the other options either. This is a tricky one!
upvoted 0 times
...
Cornell
15 days ago
Well, the setup time is definitely relevant for lead time scheduling. But I'm not sure about the other options - I'll have to think about that one.
upvoted 0 times
...
Adelle
24 days ago
I believe opening period and float after production are also important factors to consider for lead time scheduling.
upvoted 0 times
...
Shanda
25 days ago
I agree with Callie. Setup time is important to consider for scheduling production orders.
upvoted 0 times
...
Callie
27 days ago
I think setup time and total replenishment lead time are relevant for lead time scheduling.
upvoted 0 times
...